Table 2-1 Installation Checklist (Continued)
Step
Installation Task
8.
Connect the data hosts.
9.
Connect the management host.
10.
Perform initial configuration tasks:
• Set management port IP properties on the
controller enclosure
• Set the date and time on the controller enclosure
• Configure host ports on the controller enclosure
• Create virtual disks and map volumes
• Test the configuration
Installing Enclosures Into a Rack
This section describes how to install the enclosures into a standard 19-inch rack
cabinet with a 28 to 36-inch (71.12 to 91.44-cm) depth.
Preparing the Rack
Before installing enclosures in a rack cabinet, ensure the rack is installed according
to its installation instructions and that the installation complies with local safety
codes.
1. Stabilize the rack as described in its documentation.
2. If the rack has casters, make sure the casters are locked to prevent the rack from
rolling.
3. Remove or open the top front panel and the vented back panel.
Where to Find Procedure
"Connecting Hosts" on page 31
"Connecting the Enclosure Directly to
Data Hosts" on page 32
"Configuring a System for the First
Time" on page 35
Chapter 2 Installing and Cabling Enclosures
15