Summary of Contents for Huazheng Electric Manufacturing HZ-600C
Page 1
HZ-600C Transformer Winding Deformation Tester USER MANUAL Huazheng Electric Manufacturing(Baoding) Co.,Ltd...
Page 2
Dear us er: Thank you for choosingH Z -600C Tr ansfor mer Winding Defor mat ion Test er. We hope that this inst rum ent can mak e your work eas ier and more enjoyable, so that you can get the feeling of off ice aut omat ion in the test and analysis work.
Contents Contents..................................2 Attentions..................................1 System Introduction..............................3 Part I Simple Operation Flow of System......................4 Part II Preparation..............................5 Part III Test Wiring..............................5 Part IV System Test..............................7 Part V Tester Maintenance..........................13 Annex: Instructions for Installation of Transformer Winding Deformation Tester Software......14...
Attentions Please read carefully the Instructions for the transformer winding deformation tester! Operators must read carefully the Instructions before use. The tester is applicable to testing of transformer winding deformation with frequency response method. Equipment irrelevant to the tester cannot share power supply terminal with the tester. Power supply of the system must be provided with reliable grounding to prevent the risk of electric shock.
Generally, system abnormalities may be eliminated by restart of system software. Please do not use the system in rainy and foggy days as it is not water-proof. Put the tester into its packing case when not used and keep the packing case level. The scrapped equipment must be handled according to requirements of national laws and regulations or handed to the Company for handling.
System Introduction The transformer winding deformation tester is used for power transformer with voltage grade of 6kV and above and other transformers with special purpose. The power transformer is inevitably vulnerable to impulse of various fault short-circuit current or physical collision in the process of operation and transportation and the transformer windings may lose stability under the powerful electro-dynamic force exerted by such short-circuit current, which could result in permanent deformations such as local distortion, swell or dislocation and will severely affect safe operation of the transformer.
Input impedance: 1MΩ (the response channel is built with 50Ω matching resistance) Frequency scan scope: 10Hz-2MHz (10Hz-30MHz, optional) Frequency accuracy: 0.001% Frequency scan manner: linear or logarithmic, frequency sacn interval and number of sweep points are freely settable ...
Input information Select end-frequency and adjust testing parameter Select winding Start testing Replace test winding Select winding Start test Repeat above process until all winding tests are done Analyze data Export report ...
Page 9
Figure 1a Figure of Transformer Winding Deformation Tester Panel (Front Panel) Figure 1b Figure of Transformer Winding Deformation Tester Panel (Rear Panel) External wiring illustration during transformer winding deformation test is as shown in Figure 2. 3.2 Winding Wiring Mode Figure 2 Wiring type Comnect the terminal on the front panel to testee,the code of the terminal is acrroding with the code of the testee.
Part IV System Test 4.1 Start of “Winding Deformation Test System” Program Double click the icon of “transformer winding deformation tester” to start the program of “transformer winding deformation test system”. Enter the main program interface titled “transformer winding deformation tester” after the start process (double click the small icon at the top left corner of the screen to switch to the desktop.
Page 11
(B)Status Display Area The status display area displays working status of the current equipment. (C)Operating Zone There are two keys in the operating area, start and stop that display in turn according to service status, i.e. “start” displays under stop status and “stop” under start status. There is a current status display label under the key to display current status of the tester: “Offline status”: computer is working under off-line status, when only data reading and printing functions are available.
Page 12
“DSA analysis”: used for correlation analysis. Quit system. 4.2 Frequency Response Method Test Environment and Wiring Confirmation 1、 The system is wired according to requirements of 3.2 winding wiring mode. 2、 Tap position of the transformer is adjusted to the maximum impedance position (the first tap) 3、...
Page 13
Please input carefully according to the transformer nameplate while inputting information as all information is automatically saved together with the test result and incorrect input may affect the contents of the report. Scanning Mode Confirmation and Modification 1、 Selection of Scanning Mode Click “End Frequency”...
Page 14
the sake of research, generally not requiring adjustment. Test You may start data measurement with frequency response method after setting of basic test information. The system will automatically complete frequency sweep after “START” key is clicked. key will turn to key in the process of test that could stop the current scanning once clicked.
Page 15
4.4 Data Echo The system is able to echo saved data. By selecting name of power station, name of transformer, test category and time, as well as winding type and time in turn in area F, the completed test result is called out.
D: \transformer winding deformation test result\test report+ print time. doc or test report+ print time. jpg. The report could be WORD document or JPG photo, subject to the option selected in saving. Part V Tester Maintenance The section provides basic maintenance data. Please do not try to disintegrate, modify and repair the transformer winding deformation tester.
Annex: Instructions for Installation of Transformer Winding Deformation Tester Software 1、 Start up computer, and if it is once installed with the software, please first enter c:\ program files folder, select PTS folder and delete the entire folder; if the computer is not installed before, directly enter step 2.
Page 18
5、 After Confirm is clicked, the drive installation interface will display. Select Install and turn to the next step installation; 6、 Click Confirm and then click to quit instlalation. 7、 Select Confirm and turn to the next step installation.
Page 19
The dialogue box of control installation completed will display and select Confirm. 8、 Select Confirm to enter the next step installation. The system will display communication module installation program, of which the interface is as shown below: If the system is not installed with the software before, select Next Step until installation is completed. If the system is once installed with the software, the following installation interface will display.
Page 20
The installation system will install automatically until the installation interface closes automatically, indicating the system installation is completed. At the time, the executive file icon will occur on the desktop as shown below: Installation of the test software completes here. The software requires Office 2003 for output of Word documents.
Need help?
Do you have a question about the HZ-600C and is the answer not in the manual?
Questions and answers