Solar Stik PRO-Verter S 2000 AGS Setup And Operation

1kw hybrid power system (hps)
Table of Contents

Advertisement

Quick Links

SYSTEM SETUP AND OPERATION GUIDE
FOR THE
1kW HYBRID POWER SYSTEM (HPS)
DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
Version 1.0
Updated:20200611
®
June 2020
|
Solar Stik
, Inc.
PRELIMINARY DRAFT
|
1

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the PRO-Verter S 2000 AGS and is the answer not in the manual?

Questions and answers

Summary of Contents for Solar Stik PRO-Verter S 2000 AGS

  • Page 1 SYSTEM SETUP AND OPERATION GUIDE FOR THE 1kW HYBRID POWER SYSTEM (HPS) DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. Version 1.0 Updated:20200611 ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 2: Table Of Contents

    Transfer of Loads From Inverter (Batteries) to Grid / Generator......19 PV Charging Management Automatic Generator Start/Stop (AGS) Function AGS Audible Alarm Soft Start Cooling Fan Operation Protection Circuits Derating Dead-battery System Recovery Circuits Historical Data and Fault Tracking ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 3 Kit Components ..........27 PRO-Verter S 2000 AGS Description PRO-Verter Connection Ports and Vents .
  • Page 4 In-storage PMCS for 24VDC Li Expander Pak 1300 Solar Venture 300W PV Array PMCS Locking Component Cases to Prevent Tampering Human Transport of Components Warranty and Returns Return Material Authorization Warranty ABOUT SOLAR STIK, INC Contact ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 5 Figure 37. Human component transportation – Solar Venture 300 ................71 Figure 38. Human component transportation – 24VDC Li Expander Pak 1300 ............71 Figure 39. Human component transportation – 1 kW MPG ..................71 ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 6 Table 13. In-storage Preventive Maintenance Checks and Services ................68 Table 14. PV Array PMCS ............................... 69 Revision History Section Page(s) Description Date First released as a PRELIMINARY DRAFT June 2020 ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 7: General Information, Equipment Description, And Theory Of Operation

    Stik components. However, the Solar Stik architecture is modular and open allowing Operators to integrate non-Solar Stik components as part of a HPS solution. Please contact Solar Stik Technical Support for assistance in optimizing the integration of other components into a Solar Stik HPS.
  • Page 8: Important Safety Information And Instructions

    Indicates a hazardous situation which, if not avoided, could result in minor or moderate injury All safety messages will describe what the potential hazard is, how to reduce the chance of injury, and what can happen if the instructions are not followed. ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 9: Fire Hazard

    Cable connections should remain dry. • Use Sweeping Motion Unused ports on System components should • be covered when not in use to reduce the possibility of water intrusion. ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 10: Electric Shock Hazard

    Any generator connected to the System must have a neutral-to-ground bond. Figure 1. PRO-Verter grounding lug ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 11: Environmental And Handling Precautions

    SYSTEM SETUP AND OPERATION GUDIE FOR THE 1 kW HYBRID POWER SYSTEM (HPS) Environmental and Handling Precautions All Solar Stik components are ruggedized, yet there are a few things the operator can do to prevent failures and prolong the operational life of the Solar Stik System.
  • Page 12: Theory Of Operation Models Of Operation

    In the UPS model, “peak shaving” and the use of renewable power sources are also possible by connecting a Power Hub. Note about PRO-Verter model programming: The PRO-Verter is usually pre-programmed at the factory for use in the application in which it is to ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 13: Selecting A Generator/Grid Ac Source

    Note: Several programmable settings may affect the ability of the PRO-Verter to operate with a particular generator or grid AC power source. Surges and/or overloads can occur at the AC source ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 14: Energy Storage Requirements For Operation

    SYSTEM SETUP AND OPERATION GUDIE FOR THE 1 kW HYBRID POWER SYSTEM (HPS) when the transfer switch engages, causing it to shut down or overload. Consult Solar Stik Technical Support when configuring the PRO-Verter programming for a particular AC source.
  • Page 15: Pro-Verter Circuits And Functions

    PRO-Verter to restore the batteries to service using either a 120 VAC or PV power source. These circuits are not programmable. The AC-powered System recovery circuit an optional feature. Auto Generator Start/Stop 120 VAC Loads Energy Storage Figure 2. PRO-Verter S 2000 circuits ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 16: Load Prioritization

    If the load is dynamic, the PRO-Verter can make immediate adjustments and keep the total load on the AC power source from exceeding the value of the AC INPUT setting while still maintaining a 100% load at the external AC power source (generator or grid-utility). ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 17: Pass-Through" Power And The Internal Ac Transfer Switch

    Note: When switching from Inverter mode to Standby mode, the PRO-Verter waits approximately 15 seconds as it qualifies the incoming AC, ensuring the AC source is clean and stable before transferring the load. ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 18: Qualifying Ac Input Power

    AC power is immediately available for the load. The User Interface home screen will indicate that the PRO-Verter is inverting. When AC power is available from a grid-utility or generator source, the PRO-Verter is programmed ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 19: Transfer Of Loads From Grid / Generator Input To Inverter (Batteries)

    20 A and 15 A so the net charging current is 35 A, exceeding the programmed, maxiumum charging value of 20A. Note: When managing PV power using method #2, do not exceed the maximum combined rated charging current of the batteries in the bank. ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 20: Automatic Generator Start/Stop (Ags) Function

    AC loads. If there is a condition that causes the inverter to shut down, it will be reflected as a FAULT on the LCD user interface. Note: Circuit breakers will vary among PRO-Verters according to customer requirements and connection ratings. ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 21: Derating

    If circuit breakers on the AC INPUT or AC OUTPUT are tripping, it is likely that the load has exceeded the available current of the PRO-Verter and/or the generator. ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 22: Equipment Description

    Power Hubs and PRO-Verters meter voltage, current and time through the circuit, providing critical real-time data the operator can use to troubleshoot and verify System performance. Data collection enables programming/architectural changes to optimize performance based on evolving conditions. ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 23: 24Vdc Standard Inter-Connect Plug

    • Mechanically “locks” into place • Rotate knob clockwise to lock, • counterclockwise to release Can be repaired or modified in the field • Angled Straight Figure 4. Linear Inter-Connect Plug ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 24: 1Kw Hps Kit

    5-15P TO 5-15R KW WITH E-START MOD COMMUNICATION CABLE, 1KW & 2KW, 10’ 13-1000032 13-1000267 (2) 24VDC 13-1000130 (2) 24VDC INTERCONNECT INTERCONNECT CABLE, (1) 24VDC Inter-Connect Strip 7 CABLE, 5’ 5’ LINEAR ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 25: 24Vdc Li Expander Pak 1300 Description External Features

    External Features • Inter-Connect Port: Point of connection with the system 24 VDC bus, Inter-Connect network • Stacking Locks: Provide stability and alignment for stacked Expander Paks • Tech Port: Contact Solar Stik Technical Support for information. Stacking Locks (x4)
  • Page 26: 24Vdc Li Expander Pak 1300 Data Plate (D-Plate)

    SYSTEM SETUP AND OPERATION GUDIE FOR THE 1 kW HYBRID POWER SYSTEM (HPS) 24VDC Li Expander Pak 1300 Data Plate (D-Plate) Figure 6. 24VDC Li Expander Pak 1300 D-Plate ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 27: Solar Venture 300W Kit Description Kit Components

    4-section foldable PV array Ground-securing mesh (large and small) Support frame Sandbags (12 ea) Solar Cable (Part #: 16-0800102) Figure 7. Solar Venture 300W PV Array components in transport case (top) and unpacked (bottom) ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 28: Pro-Verter S 2000 Ags Description Pro-Verter Connection Ports And Vents

    SYSTEM SETUP AND OPERATION GUDIE FOR THE 1 kW HYBRID POWER SYSTEM (HPS) PRO-Verter S 2000 AGS Description PRO-Verter Connection Ports and Vents Description Connector Voltage Amps 24 VDC Expander Pak Only Inter-Connect Port Deltran 24 VDC 224-0061-BK B GEN COMM Port...
  • Page 29: Figure 10. Pro-Verter Left Side

    NEMA 5-15P B Air Intake Vent Cover Figure 10. PRO-Verter left side Description Connector Voltage Amps A 120 VAC Output NEMA 5-20R 125 VAC B Air Exhaust Figure 11. PRO-Verter right side ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 30: Pro-Verter Faceplate

    User Interface – The user interface is used to program and control the PRO-Verter and to monitor System status. The PRO-Verter is programmed at Solar Stik to meet the specifications of a specific application. Programming mode can be accessed if reprogramming is required. Contact Solar Stik Technical Support for more information.
  • Page 31 Cooling Fan 1A Breaker – The internal cooling fans are audible when functioning. Push to reset the breaker if the AC Input or AC Output port is not operating while the PRO-Verter is turned on. AGS Tech Port – Used to program the Auto Generator Start/Stop module. Please contact Solar Stik Technical Support for further information.
  • Page 32: Pro-Verter I-Plate

    (PRO-Verters and Power Hubs) to integrate with ESMs (batteries) and renewable power generation sources (e.g., PV arrays) from providers other than Solar Stik. Custom cables may be required (and can be provided by Solar Stik) to establish connections with non–Solar Stik components.
  • Page 33: Operator Instructions

    OPERATOR INSTRUCTIONS 1 Minimize Potential for Water and Dust Intrusion ALL Solar Stik equipment is designed for operation in adverse conditions, however, certain rules apply: 1 If operating in wet environments, use common-sense placement to avoid water intrusion by either flooding or precipitation.
  • Page 34: Connect Pro-Verter To Energy Storage Modules

    Expander Pak only Inter-Connect port. 24VDC Li Expander Pak 1300s Angled Plug 24VDC Inter-Connect Strip 7 24VDC PRO-Verter S 2000 * 13-1000267 Linear ** 13-1000032 Standard Figure 15. PRO-Verter to ESM connection ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 35: Connect Pro-Verter To Ac Power Source

    The PRO-Verter S 2000 can remotely start/stop the 1 kW and 2 kW man-portable generators (MPGs) (Figure 17). Ranger Defender 2 kW MPG 1 kW MPG Figure 17. Compatible generator options ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 36: Connect Pro-Verter To A Generator

    PRO-Verter to the communication port on the generator. Generator-type PRO-Verter S 2000 Selection Switch Gen Comm Port Defender 1 kW MPG Ranger 2 kW MPG Figure 18. Defender 1 kW and Ranger 2 kW Gen Comm Cable connections ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 37: Connect Pv Array(S) To Pro-Verter

    PV arrays, other than the ones provided in the kit, can be connected to the PRO-Verter as long as the power specifications for the arrays do not exceed the specifications listed on the Faceplate. Figure 20. PRO-Verter power specifications for PV arrays ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 38: Secure The Array To The Ground

    If the support frame is twisted, the array will be exposed to torsional strain, which can cause damage to the cells of the array panel(s). ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 39: Connect Pro-Verter To 120 Vac Loads

    Connect 120 VAC loads to the PRO-Verter AC output on the left side of the PRO-Verter. Connect loads of no more than 20 A. Turn off load power switches to prevent power draw during System setup. Figure 22. PRO-Verter AC power output port ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 40: Set Pro-Verter 24-Hour Clock (Time Setting)

    Select Group INPUT LOW LIMIT Select Group INPUT HIGH LIMIT Select Group OTHER FUNCTION Select Group Select Group TIME SETTING TIME SETTING Enter the time 2019/11/11 00:00 Select Group STOP SD CARD ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 41: How To Set Grid Max Current Equal To Connected Generator Or Grid Output Current

    EVO-1224 Standby CHARGE CURVE AC output: 120.0V <0.1 A 60.00Hz “Input Setting” Select Parameter Select Group INPUT SETTING INPUT SETTING DEFAULT FREQ 0=60Hz Select Parameter INPUT SETTING GRID MAX CURRENT 6.5A ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 42: Starting The Mpg With Pro-Verter

    Figure 23. Generator type and control switches; Generator Status LED blinking pattern Fuel Tank Vent Cap Lever Choke Lever AC Power Outlet ECO Throttle Switch Engine Switch Figure 24. Location of items to check before starting MPG ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 43: Operating The Pro-Verter User Interface

    • SD Card Slot—This slot supports an SD memory card (up to 16GB, FAT16/32). The SD card is used for data logging of PRO-Verter operational statistics and events and saving and uploading of programmed parameters. A dummy SD card is installed at the factory prior to shipment. ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 44: Pro-Verter Status And Alarm Leds

    Flash 2 times/sec Inverting (discharging) – alarm beep/3 sec (default off) Low battery alarm – alarm beep/1 sec Flash 1/sec Power saving Flash 1 time/3 sec Standby Flash 1 time/5 sec Fault ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 45: Pro-Verter Operating Modes

    HPS with both AC and DC loads. AC loads connected to the PRO-Verter will not be supported if the AC power source connected to the PRO-Verter fails. Charge-only mode may be used in an HPS with DC-only loads. ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 46: Operation Mode Screens

    ID= 1 EVO Ver: X.XX ID= 1 RC Ver: X.XX RC Ver: X.XX RC Ver: X.XX 2019 / 04 /21 15:00 2019 / 04 /21 15:00 2019 / 04 /21 15:00 ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 47: Pro-Verter Programmable Settings Navigating "Select Group" And "Select Parameter" Menu Maps

    Group 4 Select Group Screen #5 OTHER FUNCTION for Group 5 Select Group Screen #1 TIME SETTING for Group 6 Select Group Screen #1 STOP SD CARD for Group 7 ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 48: Parameter Groups: Pro-Verter Programmable Settings

    Power Saving/Alarm/Remote Switch/Multi-function Relay/etc. Group 6 TIME SETTING Local time clock setting. Shown only when SD card is inserted. Group 7 STOP SD CARD To stop SD card and to remove the SD card. ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 49: Charge Curve Programmable Settings

    SYSTEM SETUP AND OPERATION GUDIE FOR THE 1 kW HYBRID POWER SYSTEM (HPS) Please contact Solar Stik Technical Support before changing settings other than the clock or the AC Input settings These settings are highlighted orange in the tables that follow Charge Curve Programmable Settings Parameters in this group define System battery charging protocols.
  • Page 50: Input Setting Programmable Settings

    If the load reduces to 1 A less than the programmed value of Grid Max Current/Gen Max Current for 5 sec, the PRO-Verter will switch back to Charging mode. INPUT RECOVERY DIRECT Option 1 = Direct: The PRO-Verter will start in Charging mode. ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 51: Input Low Limit Programmable Settings

    > Detect Time 3, the PRO-Verter will transfer to Inverting mode. This is the time limit in cycles up to which the low AC input voltage Cut DETECT TIME 3 1 Cycle Off Volt 3 is allowed. ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 52: Other Functions Programmable Settings

    This is to reset all of the parameters to the factory values. The factory DEFAULT RESET 0 = NO values are not the program values set by Solar Stik. A real time clock inside the user interface records timing. The time interval DATA LOG TIME 2 = 10 sec between recordings is programmable.
  • Page 53: Saving/Uploading Programmed Parameters Saving Programmed Pro-Verter Parameters To Sd Card

    BACK key to cancel. • Asks to confirm or cancel uploading of saved parameters. Upload Conf? Yes=Enter key • Choose Yes by pressing ENTER key. No=Back key Upload Conf Configuration uploading. 1%.. ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 54: Pro-Verter S 2000 Data Logging

    Below is an image of the DATALOG folder showing example of the Data Log Files. The file name format is month/day/hour/minute.txt (MMDDhhmm.txt). Each file has 512 rows of records. (Each row has multiple data fields.) Each file size is 128 KB. ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 55 • Click on “File Types” selection button at the bottom right corner (shows “All Excel Files” as default) and select text files from the drop-down menu. • All text files (.txt) will be displayed. Click “Open” button ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 56 SYSTEM SETUP AND OPERATION GUDIE FOR THE 1 kW HYBRID POWER SYSTEM (HPS) Text Import Wizard – Step 1 will be shown. Choose “Delimited” file type. Text Import Wizard – Step 2 will appear. Choose “Semicolon” and click Finish button. ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 57: Figure 27. 1 Kw Generator Duty Cycle As A Function Of Continuous Loads

    The first case demonstrates the 1 kW generator duty cycle in the HPS as a function of a series of continuous loads. This case assumes no PV contribution. Generator Duty Cycle vs Load Load (W) Load (W) Figure 27. 1 kW generator duty cycle as a function of continuous loads. ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 58: Figure 28. System Runtime At Various Loads With Pv Power Only

    100 W 150 W 200 W 250 W 300 W 350 W 400 W 450 W 500 W Load Load (W) Figure 28. System runtime at various loads with PV power only ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 59: Figure 29. Increaseing Pv Power Input Reduces Generator Duty Cycle

    Duty Cycle, 300 kW PV, 4 solar hours/day Load (W) Duty Cycle, kW PV, 5 solar hours/day Duty Cycle, kW PV, 6 solar hours/day Figure 29. Increaseing PV power input reduces generator duty cycle. ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 60 5. AC INPUT LED illuminates (~ 2 min after start). 6. PRO-Verter qualifies generator power. 7. Charging begins (see PRO-Verter user interface). 8. Rapidly toggle Generator Control switch to AUTO to begin normal hybrid operation. ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 61: Figure 30. Measuring Pv Array Open Circuit Voltage V

    Contact the FSR if a PV array voltage measurement indicates that a PV array is either not functioning or is performing very poorly. The rated V for the array is 65 V 30’ Solar Cable A(-) C(+) Figure 30. Measuring PV array open circuit voltage V ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 62: Table 11. Fault Messages Symptoms And Troubleshooting

    (Note: A voltage this low will not be encountered when using LiFePO batteries Battery ultra because the battery’s own BMS will disconnect the output terminals before the voltage low voltage! drops that low ) Continued on next page ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 63 Ensure that the maximum, instantaneous surge current of the load is NOT more than 300% (30 A) of the rated current (10 A) of the inverter for more than 1 millisecond. Continued on next page ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 64 Ensure the fans are working properly, there is no blockage of air flow, there is adequate airflow, and the ambient temperature is within the limits. Reduce the load/Bulk Current. • The fault will clear when the transformer has cooled down to 80°C. Continued on next page ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 65 The entered value of programmable parameter could not be written. The entered value of programmable parameter is out of the programmable range. Change OUT OF RANGE! parameter value to within the specified range. ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 66: Figure 31. Fastener Locations On Vent Shroud (Upgraded/New Version)

    1 Use a #2 cross-tip screwdriver to remove the four (4) fasteners from the vent shroud and remove the louvered vent cover to access the filter. Figure 31. Fastener locations on vent shroud (upgraded/new Figure 32. Removed vent shroud to access the version) louvered vent cover ® PRELIMINARY DRAFT June 2020 Solar Stik , Inc.
  • Page 67: Figure 33. Replacing Pro-Verter Filter (Left); Cleaning A Pro-Verter Filter (Right)

    Figure 33. Replacing PRO-Verter filter (left); cleaning a PRO-Verter filter (right) 3 Reinstall the clean, dry filter or install the new filter. Secure the vent shroud with the four (4) fasteners. ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 68: Table 13. In-Storage Preventive Maintenance Checks And Services

    In-storage PMCS for 24VDC Li Expander Pak 1300 Failure to follow these instructions may result in permanent equipment failure and/or personal injury Required Tools Solar Stik PRO-Verter or LiFePO4 battery maintenance charger. Table 13. In-storage Preventive Maintenance Checks and Services Item to be Interval*...
  • Page 69: Table 14. Pv Array Pmcs

    PV array cannot be secured Inspection are full and situated properly. to the ground, the PV array is NMC. Contact Solar Stik to of PV array ground 3. Ensure that none of the sandbags repair or replace the PV array.
  • Page 70: Figure 36. Human Component Transportation - Pro-Verter S 2000

    SYSTEM SETUP AND OPERATION GUDIE FOR THE 1 kW HYBRID POWER SYSTEM (HPS) Locking Component Cases to Prevent Tampering Solar Stik Component can be secured with a padlock to deter tampering. Four (4) latches allow the case to be sealed to prevent damage to the internal components from environmental factors.
  • Page 71: Figure 37. Human Component Transportation - Solar Venture 300

    The 1 kW MPG has a dry weight of 39.1 lbs (17.7 kg), has a handle on top and can be carried by a single person. Figure 39. Human component transportation – 1 kW MPG ® June 2020 Solar Stik , Inc. PRELIMINARY DRAFT...
  • Page 72 1 Solar Stik warrants, unless otherwise agreed to between buyer and seller (Solar Stik, Inc.), for a period of one (1) year from Solar Stik’s delivery of such Products, the Products shall be free from defects in materials and workmanship and shall conform to the contractual specifications or to specification sheet of the Product.
  • Page 73 • Solar Stik New Equipment Training (on site) teaches Hybrid System configuration options with hands-on deployment of actual systems to enhance student understanding. Solar Stik Training Courses are tailored to the specific needs of the students. To schedule Solar Stik Training or to learn more about the curriculum, please contact us.

Table of Contents