Faults

The following chapter describes possible causes of faults and the work needed to rectify them. Should faults occur frequently,
shorten the maintenance intervals in line with the actual loading on the unit.
Contact the manufacturer with any faults that cannot be rectified using the following information.
Behaviour in the event of faults
The following applies:
1. Immediately switch off the unit with faults that pose an immediate danger to persons or property!
2. Determine the cause of the fault!
3. Switch off the unit and prevent it from being reconnected if rectifying the fault requires work in the hazard area. Immedi-
ately advise a supervisor on site about the fault.
4. Either rectify the fault yourself or have it repaired by authorised personnel, depending on the nature of the fault.
The Fault table [} 28] provides information on who is authorised to rectify and remedy faults.

11.1 Fault table

Fault
No function.

11.2 Start-up after rectification of fault

After correction of the fault, carry out the following steps for recommissioning:
1. Make sure that all maintenance covers and access openings are sealed.
2. Switch off the unit.
3. Acknowledge the fault on the controller, if necessary.
28
Possible cause
No power supply.
Remedy
Check voltage, switch on repair switch.
Replace fuse.