Installation Procedure
Method 1
Connection sleeve
4 Using a crimping tool, compress the two points and flip
it over and compress another two points in the same
location.
• The compression dimension should be 8.0
• After compressing it, pull both sides of the wire to
make sure it is firmly pressed.
Method 1
Compress it 4 times
5mm
5 Wrap it with the insulation tape twice or more and
position your contraction tube in the middle of the
insulation tape.
Three or more layers of insulation are required.
Method 1
Insulation tape
40mm
6 Apply heat to the contraction tube to contract it.
Contraction tube
18
English
Method 2
Connection sleeve
Compression
dimension
Method 2
Compress it 4 times
5mm
Method 2
Insulation tape
35mm
7 After tube contraction work is completed, wrap it with
the insulation tape to finish.
CAUTION
• Make sure that the connection parts are not exposed
to outside.
• Be sure to use insulation tape and a contraction tube
made of approved reinforced insulating materials
that have the same level of withstand voltage with
the power cable. (Comply with the local regulations on
extensions.)
WARNING
• In case of extending the electric wire, please DO NOT
use a round-shaped Pressing socket.
‐ Incomplete wire connections can cause electric
shock or a fire.