Base construction and installation of the DVM Hydro unit

• If this product is installed in residential area, apply anti-vibration product to prevent the vibration from
transferring to the building.
WARNING
f Manufacturer is not responsible for the damage occurred by not following the installation standards.
1. Considering the vibration and weight of the DVM Hydro unit, strength of the base ground must be strong enough to
prevent noise and the top part of the base ground has to be flat.
2. Base ground should be 1.5 times larger than the bottom of the Hydro unit.
3. It is necessary to add wire mesh or steel bar during concrete construction for the base ground to prevent damages or
cracks.
4. Place the DVM Hydro unit on the base construction and completely fix it with the bolt, nut and washer. (The bearing force
has to be over 3.5kN)
5. Fix the DVM Hydro unit firmly with 4 foundation bolts.
6. When concrete construction for DVM Hydro unit installation is completed, install an anti-vibration pad(t=20mm or
more) or an anti-vibration frame(vibration transmissibility=5% and below) to prevent vibration of the outdoor unit from
transferring to the base ground.
7. When constructing base ground, DVM Hydro unit must be supported within the range of following dimensions.
Base ground construction
Drain hole
200mm or more
Outdoor unit installation
340
518
DVM HYDRO UNIT_IM_E_03469A(1).indd 7
(Unit: mm)
Anchor bolt
Nut, Spring
washer
DVM Hydro unit
20mm
Anti-vibration pad
H beam or anti-
A
vibration frame
A+10~20mm or more
7