Refrigerant piping

Piping connections are inside the front panel of the
unit and the front panel and pipe cover needs to be
removed before piping and wiring connections are
made.
Piping can enter the outdoor unit from the back, from
the side or from the bottom as shown
Front panel
Pipe cover
Rear
Side
Bottom
1. Remove the front panel of the unit.
2. Remove the pipe cover.
3. Remove the appropriate knockout depending on the
orientation of the piping.
The pipe cover is easily mounted by cutting off
the slit at the lower part of the pipe cover.
*
Be sure to wear heavy work gloves while working.
4. Remove the burrs from the knockout opening and
use the factory supplied protective edge guard
material around the opening to protect the piping
and the wiring.
5. Remove the flare nut from the service valve on
outdoor unit. Insert the flare nut into the field piping,
and flare the pipe.
Bend the pipe approx. 90 degree with a pipe bender
for side and rear piping.
6. When the piping connections are complete re-install
the pipe cover.
17-EN
1131601101 EN FR ES.indb 9
1131601101 EN FR ES.indb 9
Flaring
1. Cut the pipe with a pipe cutter.
Be sure to remove burrs that may cause a gas
leak.
2. Insert the supplied flare nut into the pipe, and then
flare the pipe.
As the flaring sizes of R410A differ from those of
refrigerant R22, the flare tools newly manufactured
for R410A are recommended.
However, the conventional tools
B
can be used by adjusting the
projection margin of the copper
pipe.
▼ Projection margin in fl aring : B (Unit : in (mm))
Rigid (Clutch type)
Conventional
R410A tool used
Outer diameter of
tool used
copper pipe
R410A
0.04" - 0.06"
3/8" (9.5)
(1.0 - 1.5)
0 - 0.02" (0 - 0.5)
5/8" (15.9)
▼ Flaring diameter size : A (Unit : in (mm))
Outer diameter of copper pipe
A
+0
-0.02"(–0.4)
3/8" (9.5)
0.52" (13.2)
5/8" (15.9)
0.78" (19.7)
*
In case of fl aring for R410A with the
A
conventional fl are tool, pull the tool out
approx. 0.02" (0.5 mm) more than that for
R22 to adjust it to the specifi ed fl are size.
The copper pipe gauge is useful for
adjusting the projection margin size.
– 9 –
Tightening of Flare
Connections
1. Align the centers of the flare connections and fully
tighten the flare nuts with your fingers.
Valve at liquid side
Cap
Loosened
Piping valve
Tightened
Flare nut
2. Use two wrenches to loosen or tighten the flare nut
on the gas service valve as shown in the figure.
Use only one wrench to loosen or tighten the flare
not on the liquid service valve.
The final tightening with a torque wrench should be
to the specifications shown in table below.
Unit : ft•lbs (N•m)
Outer diameter of copper pipe
Tightening torque
3/8" (9.5 mm)
24 - 31 (33 - 42)
5/8" (15.9 mm)
50 - 60 (68 - 82)
Valve at gas side
Cover
Cap
Piping valve
Charge orifice
Flare nut
Tightened
Loosened
After the installation work, be sure to check for gas
leaks of the pipe connections with nitrogen.
NO GOOD
NO GOOD
Cover
Charge orifice
CAUTION
1. Do not put the crescent wrench on the charge
orifice or cover.
The valve may be broken.
2. If applying excessive torque, the nut may break
according to some installation conditions.
Pressure of R410A is higher than that of R22
(Approx. 1.6 times).
Therefore, using a torque wrench, tighten the flare
pipe connecting sections that connect the indoor/
outdoor units at the specified tightening torque.
Incomplete connections may cause not only a gas
leak, but also trouble with the refrigeration cycle.
Do not apply refrigerant oil to the flared
surface.
4/8/2565 BE 10:14