6. Assemble the cable above ground in the blade.
7. Plough the two cables at the same time up to the
point indicated in the figure (G). Fasten the two
cables to a stake and unhook the second cable from
the blade.
G
START
10
8. Continue the work by ploughing the perimeter cable.
Refer to the figure (H).
H
STOP
To adjust the blade
The product is adjusted for 4 mm cables. If the cable
has greater diameter, the blade need to be adjusted.
1. Loosen the 2 screws.
2. Raise the blade a few millimeters.
3. Tighten the 2 screws.
To clean the blade
The product is provided with a blade scraper for
cleaning the blade