Operation Of Hsc Pump; Precommisonning Checks; Starting - DECCAN DP 50/30A Installation, Operation And Maintenance Manual

Table of Contents

Advertisement

I N S T A L L A T I O N , O P E R A T I O N A N D M A I N T E N A N C E M A N U A L
Foundation Plinth
alignment.
5. OPERATION OF HORIZONTAL SPLIT CASE PUMPS.
In order to ensure satisfactory operation of t pumps, review carefully and perform all the
operation outlined as below.

5.1. PRECOMMISONNING CHECKS.

 Check the pump bearings are fitted with sufficient amount of lubricant.
 In addition to the above, it is advisable to check the motor bearings for lubrication.
This should be done in accordance manufacturer's recommendation as listed in the
motor installation manual.
 When possible, turn the pump shaft by hand to insure that the parts do not bind.
 Motor is correctly wired to starting device, check voltage, phase and frequency on
motor name plate with line circuit.
 Before the coupling alignment, check the drive rotation to see that it matches the
pump rotation. Pump rotation is indicated by arrow in the pump casing.
 The unit base plate is grouted and bolted to the foundation.
 Alignment between pump and motor.
 Fill the suction with liquid and check for leakage of joints. Tighten the leaking joints
or replace gaskets where ever necessary.

5.2. STARTING

 Close the discharge line valve.
 Open fully in suction line valve if provided.
 Turn on seal water to the stuffing box where external pipe supplied.
 Prime the pump I one of the following ways.
 If the pump operates under positive suction conditions, open vent valve on the
top of the pump casing. After all entrained air has escaped, closed the vent
13 |
P a g e
CHECK DISCHARGE DISCHARGE INCREASER VALVE VALVE PIPE
After all the piping is complete, recheck the pump and driver
Check Valve
Support