V.
of dam. Adequate care should be taken while pouring the grout, to avoid
formation of air bubbles. This can be achieved either by stirring of the grout by
a vibrator or directly pumping of grout into place.
VI.
foundation bolts and check the alignment.
VII.
thoroughly dry, apply an oil based paint to exposed the edges of the grout to
prevent air and moisture from coming in contact with the grout.
3.6
The unit should be periodically checked for alignment. If the unit does not stay in line
after being properly installed, the following are possible reasons:
4. SUCTION AND DISCHRGE PIPING.
When installing the pump piping, make be sure to observe the following precautions.
 Piping should be always run up to the pump. Do not move pump to pipe as this may
make final alignment impossible.
 Both suction and discharge piping should be properly aligned and supported
independently near the pump, so that no strain is transmitted to the pump when the
flange bolts are tightened.
 Install piping as straight as possible, avoiding unnecessary bends, where ever
necessary, use long radius 45-degree or 90-degree bends to decrease friction
losses.
 Remove burrs and sharp edges when making up the pipe joints.
 Make sure that all piping joints are air –tight.
11 |
P a g e
Pour grout through the grout hole into the base plate up to the level
After the grout has hardened (usually 48 Hours) thoroughly, tighten
Approximately days after the grout has been poured or when it is

FACTORS THAT MAY DISTURB ALIGNMENT.

Setting, seasoning of the foundation.
Pipe strains, distorting or shifting of the units.
Wear of bearings.