Commissioning And Adjustment - Viessmann WAGO 750-8212/000-100 Installation And Service Instructions For Contractors

Bms communication with heating systems via bacnet, bacnet/ip gateway
Table of Contents

Advertisement

Commissioning and adjustment

Commissioning the gateway
Commissioning must be carried out by the IT expert or
system integrator.
1. Switch on the heat generator.
2. Switch on the power supply for the gateway.
3. Check the status of the LED for standard mode
after switching on: See the following table.
If the LED indicators do not match the table, check
the connections: See overview on page 13.
LED indica-
Status of the LED for standard
tors
mode
SYS
Green
RUN
Green
I/O
Green
MS
Off
NS
Off
U1
Green
U2 - U6
Off
BT
Green
Note
If the LED lights up red or yellow, a
BACnet-specific error is present.
Clarification with system integrator
is required
24
4. For further commissioning steps, see the "WAGO
BACnet Automation Gateway commissioning man-
ual" at www.automation-gateway.info
Note
CAN ID window defined for the LAG devices (77). All
LAG devices must be arranged in this address space,
otherwise they cannot be made available to the BMS.