Commissioning And Adjustment - Viessmann WAGO MB/TCP gateway Installation And Service Instructions For Contractors

Bms communication with heating systems via modbus
Hide thumbs Also See for WAGO MB/TCP gateway:
Table of Contents

Advertisement

Commissioning the gateway
Commissioning must be carried out by the IT expert or
system integrator.
1. Switch on the heat generator.
2. Switch on the power supply for the gateway.
3. Check the status of the LED for standard mode
after switching on: See the following table.
If the LED indicators do not match the table, check
the connections: See overview on page.
LED indica-
Status of the LED for standard
tors
mode
SYS
Green
RUN
Green
I/O
Green
MS
OFF
NS
OFF
USR
Green

Commissioning and adjustment

4. For further commissioning steps, see the "WAGO
Modbus automation gateway commissioning man-
ual" at www.automation-gateway.info
27

Advertisement

Table of Contents
loading

This manual is also suitable for:

Wago mb/rtu gateway

Table of Contents