User Manual A100 / A200 / A300 Optical Fibre Probe Copyright Dipl.- Ing. Gunter Langer Nöthnitzer Hang 31 01728 Bannewitz 17.01.2000 Voltage measurement and oscillographic signal tracing in devices and systems under extreme electromagnetic conditions. 2018.10.19 A100-200-300 User manual.doc...
Connection of the probe (example AS 100) to the DUT Starting the AE XXX optical receiver 4 Safety instructions 5 Warranty 6 Technical data System Sensors Receivers 7 Scope of delivery A100-1 / A200-1 / A300-1 (1-channel) set A100-2 / A200-2 / A300-2 (2-channels) set - 2 -...
The task is to correctly measure these relatively slow disturbance signals under extreme RF interference conditions. The A100 / A200 / A300 measurement systems are ideal for these conditions because of their high disturbance immunity.
LANGER DE-01728 Bannewitz A100 / A200 / A300 mail@langer-emv.de EMV-Technik www.langer-emv.com 1.6 Examples of disturbed useful signals - Signals were measured with the AS 100 optical fibre probe - Radiated RF emissions: 250 MHz, 80 % amplitude-modulated by 1 kHz - DUT: operational amplifier circuit;...
Page 5
LANGER DE-01728 Bannewitz A100 / A200 / A300 mail@langer-emv.de EMV-Technik www.langer-emv.com Figure 4 Useful signal without interference Figure 5 Useful signal with 1 kHz disturbance signal Figure 6 Useful signal with 1 kHz disturbance signal limited by the upper rail...
LANGER DE-01728 Bannewitz A100 / A200 / A300 mail@langer-emv.de EMV-Technik www.langer-emv.com 2 Function 2.1 Method of measurement An RF-immune probe (AS 100, AS 110, AS 120, AS 200, AS 300 or AS 350 optical fibre probe), of which the A/D (analog-to-digital) converter is an integral part, is autonomously operated in the DUT without interfering with the DUT's EMC conditions.
LANGER DE-01728 Bannewitz A100 / A200 / A300 mail@langer-emv.de EMV-Technik www.langer-emv.com 3 Operation 3.1 Connection of the probe (example AS 100) to the DUT Figure 8 AS 100 pin assignment Attention: Only connect and disconnect an AS XXX sensor when it is not subjected to any interference.
LANGER DE-01728 Bannewitz A100 / A200 / A300 mail@langer-emv.de EMV-Technik www.langer-emv.com Figure 9 AS 100 connected to the DUT; position the AS 100 on the IC package if there isn't enough free space above 3.2 Starting the AE XXX optical receiver - Connect the AE XXX to the oscilloscope (BNC plug).
Read the operating and safety instructions for all devices used in the set-up. Never use any damaged or defective devices. Carry out a visual check before using a measurement set-up with a Langer EMV-Technik GmbH product. Replace any damaged connecting cables before using the product.