PCS100 AVC-40 Commissioning Checklist
1.11 Load Test
No
Description
71.
Switch the load on.
Start the PCS100 AVC-40. Verify the PCS100 AVC-40 enters RUN mode and no faults
exist.
72.
Check the voltages on the GDM status screen are as expected. The output voltage
should be ~ 100% of the 600 V Set Manual value.
73.
Check the load currents on the GDM status screen match the actual measured load
currents within tolerance. Ensure greater than 5% load current is applied for this
check.
74.
Check the loading level < 100% on GDM status screen.
75.
Check no overload is shown on the GDM unless greater than 10% voltage correction
is being provided.
1.12 Documentation and Handover
No
Description
76.
Connect a PC to the PCS100 AVC-40 via the GDM USB and run a web browser on the
PC. Download and save the Service Log for future use or reference. See document
2UCD200000E001 How to View the GDM Remote Web Pages for detailed instructions .
77.
In the PCS100 AVC-40 Settings below record the settings that have been changed
78.
Ensure the correct user documentation or manuals are available within the system, or
accessible by staff.
79.
Place or store other documentation at appropriate locations.
80.
Provide training to appropriate staff.
81.
Ensure plant staff knows the system is now in service.
82.
A copy of this checklist and the Service Log must be sent to ABB Power Conditioning
Products or emailed to nz-powerconditioningservice@abb.com. Failure to comply
with this may affect any possible future warranty claims.
Check