PCS100 AVC-40 Commissioning Checklist
1.2 DIP Switch Settings
Check the DIP switch settings of the various components within the system if they have been replaced or have
changed prior to commissioning. Note these switches are all set at the Factory as part of the production test
process.
Note:
The following pictures may not represent actual settings for this unit, refer to the appropriate table.
No
Description
15.
Check the DIP switch settings on the CAN Termination Board.
The CAN Termination Board is mounted on the right hand side of the Master
Controller Enclosure.
SW1 (bottom) has DIP switches 3-5 set to OFF. Switches 1,2 and 8 are set to ON.
Switches 6,7 can be set to ON or OFF.
* SW2 (top) is not used therefore DIP switches can be set ON or OFF
SW3 (middle) has DIP switches 1 & 2 set to OFF and 3 & 4 set to ON.
Text...
SW2
*
1 ANY
2 ANY
3 ANY
4 ANY
SW3
1 OFF
2 OFF
3 ON
4 ON
SW1
1 ON
2 ON
3 OFF
4 OFF
5 OFF
6 ANY
7 ANY
8 ON
Check