PCS100 AVC-40 Commissioning Checklist

1.5 Change Frequency from 50Hz to 60Hz (if required)

If the PCS100 AVC-40 needs to be changed from a 50Hz to a 60Hz machine.
No
Description
29.
Unplug the DB9 cable to the Auxiliary Master Module from VR1 and VR2
30.
This is not applicable to all models as some MCCBs do not have frequency settings.
Check the switch settings on the MCCB and if there is a frequency setting adjust this
to the 60Hz setting. Do not adjust any other settings on the MCCB.
31.
Perform the power up procedure as described in Section 1.6. up to step 42.
32.
Power down the PCS100 AVC-40 and reconnect VR1 and VR2 to the Auxiliary Master
Module.
33.
Turn power on again to the PCS100 AVC-40 and continue from step 43.
1.6 Initial Power Up – Utility Supply
All loads should remain disconnected at this stage.
No
Description
34.
Check all protective covers are in place.
35.
Ensure the Stop – Enable switch is set to Stop.
36.
Apply utility power to the PCS100 AVC-40 and verify the system has energised
correctly.
37.
Verify the red LED on top of the Auxiliary Master Module and any Auxi liary Slave Module
is on. This indicates the 26.5 volts DC power supply is operational.
38.
Once the automatic start-up and configuration check has been performed verify the
blue LED on top of the master module is flashing. This indicates the DSPE micro is
running
39.
Verify the inverter and rectifier modules power up correctly by checking the module
display board status LEDs. Refer to the PCS100 AVC-40 User Manual for descriptions
of these LEDs. The OK LEDs should be on and the run LEDs should be off. Check the
module identification numbers are unique. Resolve any abnormal condition before
continuing with this checklist. L0 remaining on the module display boards indicates a
fatal error in the System Configuration Manager (SCM). The exact error code will be
signaled by the flashing LED on the SCM board. (Refer to ABB document no
2UCD200000E430 SCM diagnostics
40.
Verify the GDM powers up, if not confirm the GDM is turned on by pressing the small
button on the GDM rear panel (left hand end). It will initially show defau lt start-up
screens.
Successful configuration check will be indicated by the GDM displaying the Status
Page, and no configuration errors being reported.
The GDM control panel should show 'Inhibit' indicating the system is inhibited from
starting by the Stop – Enable switch. The GDM should show Status: BYPASS indicating
the bypass condition of the unit.
41.
On the GDM, access the Menu page and select 00 Password and enter the correct Tech
password to change to the Tech menu
).
Check
Check