PCS100 AVC-40 Commissioning Checklist
42.
Check 13 Supply Voltage and 14 Supply Frequency are correct for the application.
Adjust if necessary.
43.
Check 12 Transformer Config is set correctly for the application.
This parameter is set by default to "Top Input", but if the transformer wiring was
changed for "Bottom Input" (contact the Factory for the procedure to perform this
change), then this parameter must be checked and changed accordingly to "Bottom
Input".
44.
Check 600 V Set Manual setting is correct for the application. Adjust if necessary.
45.
Check 601 V Set Source is set to MANUAL.
46.
Check the Customer's requirements and set 27 Auto Start and A63 SSH Port Enable
accordingly.
47.
If any faults are present and reported on the display then resolve these faults before
continuing.
48.
If Modbus TCP or remote webpages are to be used adjust the network configuration
parameters B11 to B14.
49.
Enter the company, site and plant via parameters 02, 03 and 04. (Entering the Operator
or Tech password is required).
50.
Verify the Input Voltage and Output Voltage (and Frequency if possible) measurements
shown on the GDM status screen are correct with a true RMS meter.
51.
Verify all the rectifier, inverter module fans are running and exhausting correctly (check
air flow at rear).
52.
Verify all transformer fans (if applicable) are running correctly.
53.
Check the GDM s/w revision is up to date using the GDM Software Upgrade Tool.
54.
Power down the PCS100 AVC-40.
55.
Set the Stop – Enable switch to Enable.
56.
Ensure the doors are closed and then re-power the PCS100 AVC and allow the
configuration check to complete. Following this verify the INHIBIT is now removed
from the Status Bar on the GDM.