E31E Series Installation Guide
General SNMP
Programming
Information

Commissioning

Z206855-0D
Page 28 of 35
Alta Labs, Enercept, Enspector, Hawkeye, Trustat, Aerospond, Veris, and the Veris 'V' logo are trademarks or registered trademarks of Veris Industries, L.L.C. in the USA and/or other countries.
The E31E can be configured to support the SNMP V2c protocol over Ethernet. The SNMP community string and the IP address for
the client receiving SNMP V2c event notifications can be set via the GUI. MIB files are available for download at
www.veris.com/SNMP.aspx to enable accessing the E31E from an MIB browser.
The E31E OID structure organizes the data under two "panels" representing the two breaker panels that can be monitored by a
fully populated E31E. Panel 1 corresponds to the CT strips connected to the "Panel 1A" and "Panel 1B" connectors and to the data
set under Modbus address 1 or BACnet device identified as Node_1 in the GUI. Panel 2 corresponds to the CT strips connected to
the "Panel 2A" and "Panel 2B" connectors and to the data set under Modbus address 2 or BACnet device identified as Node_2 in
the GUI.
For each panel, data is arranged under six tree branches.
• The Configuration branch contains all writable configuration parameters.
• The Alarms branch contains all the alarm notification traps, the global alarm status registers and counters and tables
of the alarm status indicators.
• The Voltage Inputs branch contains all data measurements pertaining to the voltage inputs.
• The Auxiliary Inputs branch contains all data measurements pertaining to the aux inputs other than voltage-related.
• The Branch Inputs branch contains all data measurements to the branch inputs in table format.
• The Flex Circuits branch contains all data measurements to the logical meter summaries in table format.
HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH
• Follow safe electrical work practices. See NFPA 70E in the USA, or applicable local codes.
• Replace all doors, covers and protective devices before powering the equipment.
Failure to follow these instructions will result in death or serious injury.
1. Reconnect power to the panel.
2. Configure installation mode using Modbus Register 6.
3. Configure CT scaling.
4. Configure alarms.
5. Configure demand.
Download the free E3xE configuration tool from www.veris.com to commission the device for operation.
©2020 Veris Industries USA 800.354.8556 or +1.503.598.4564 / support@veris.com
Other companies' trademarks are hereby acknowledged to belong to their respective owners.