Adapter plate installation
1.
Place the adapter plate in the desired position on the formwork with the rubber seal, as specified in the construc-
tion plan. (If necessary, attach the pipe support KWL-MZB-RH 7 or KWL-MZB-RH 13 with the screws from the
accessories kit).
In order to prevent the construction or pipe from floating during concreting, the adapter plate can be attached to
the formwork with nails.
If a pre-made ceiling element (filigree ceiling) is used as a substrate, the opening should be made 6 cm larger on
all sides, so that the gap between the ceiling element and connection plate is optimally filled during concreting.
2.
Remove the dust protection caps on the required connectors. The shorten the FlexPipe
to the grooves, insert a seal in the 3rd trough and insert up to the stop in the corresponding connectors.
The connectors only ensure a secure connection if the pipe has been shortened, the seal has been inser-
ted and the pipe is pressed over the groove in the connector .
Fig .1
Installation WITH pipe support KWL-MZB-RH 7 or KWL-MZB-RH 13:
3.
Loosen the two screws in the respective securing bracket of the pipe support KWL-MZB-RH 7 or KWL-MZB-RH
13 and release the securing bracket.
4.
Bend the pipe 90° and mount to a pipe outlet in the pipe support KWL-MZB-RH 7 or KWL-MZB-RH 13.
Then fix the pipes with the securing bracket and insert the screws in the securing bracket.
Installation WITHOUT pipe support:
3.
Bend the pipe 90° and insert into the respective connector (do not forget the seal in the 3rd trough). Fix the pipes
to the reinforcement so that it cannot be pulled out (reinforcing wire or similar).
Ensure the correct assignment of supply air and extract air, as this can no longer be subsequently
amended!
4.
Concreting of connection plate including the FlexPipe
2 .1
Connect MultiZoneBox to adapter plate
Once the concrete has set, remove the formwork and check that all pipe connections and insert nuts are clean; rework
accordingly, if necessary.
Risk of accidents and injuries during installation and servicing!
At least two people and/or one suitable lifting device are required to install the MultiZoneBox.
Fig .2
plus
pipes.
Fig .4
2
plus
pipes parallel
Fig .3

Advertisement

loading