Mechanical and electrical installation
Install the energy meter on a DIN rail in the
2
distributor.
y The distance to the current transformers is
determined by the connection cables of the
transformers.
Locate the cables for current measurement in the
3
distributor.
Connect the energy meter to the mains via specially
4
fused cable taps (F = 315 mA).
y Assign the screw terminals 7, 8, 9 and
! on the energy meter in accordance with the
connection mode selected (  page 14).
Connect the fixed connection cables of the current
5
transformers to the energy meter.
y Assign the connection terminals 1, 2, 3,
4, 5 and 6 on the energy meter in accord-
ance with the connection mode (see table next
page).