Before installing the device, read the user manual carefully to get familiar with product information and safety precautions. Huawei shall not be liable for any consequence caused by violation of the storage, transportation, installation, and operation regulations specified in this document and the user manual.
Page 3
(6) Evaporator (7) Spray pump (8) Air supply fans (9) Compressor (10) Compressor drive (11) Water tank (12) Fan drive Item FusionCol8000-E240 Scenario FDC scenario Building scenario Power system 380–415 V AC, three-phase, 50 Hz/60 Hz 11,000 kg 5000 kg...
Page 4
Materials delivered Refer to the material list. with the unit Optional component Motorized damper, electric heater, and T/H sensor Local Water pipe Water refill pipe of the water tank: G 3/4 inch inner thread connector procur (DN25) ement Condensate drainpipe of the evaporator: G 3/4 inch inner thread ...
Page 5
Securing the FusionCol8000-E • Before installation, read the related user manual to understand the product information. • Ensure that the concrete platform levelness meets the requirements. • Install the equipment in strict accordance with the HVAC equipment construction specifications. Securing the FusionCol8000-E (FDC Scenario) Reserved Ports for Combined Installation Connect the hoisting ropes and hoist the equipment to the installation area.
Page 6
Securing the FusionCol8000-E (Building Scenario) When marking the platform position, ensure that the four lines form a rectangle. When the equipment is installed indoors, it is recommended that shock pads be installed between the air duct and the floor. •...
Page 7
3. Secure the equipment to the concrete 2. Connect the hoisting ropes and hoist the platforms using right angle brackets. equipment onto the concrete platforms. Ground the equipment. Ground lugs or ground cables can be used to ground the equipment. There are two ground ...
Page 8
(Optional) Installing Electric Heater Components Building Scenario FDC Scenario Open the maintenance door for the Remove the air exhaust side panel. electric heater controller to be Install the electric heater controller. installed. Route the heating belt and Install the electric heater controller. temperature sensor probe through Route the electric heating belt and the condensate drainage hole, wrap...
Page 9
Installing Water Pipes • The water pipes are connected using thread connectors. The threaded joints must be sealed with sealing tape or thread adhesive. • Clean the external water pipes before connecting them to the water inlet and outlet pipes. •...
Page 10
Drainpipe Routing (Pipes Routed from the Bottom) (1) Main drainpipe (2) Water trap Drainpipe Routing (Pipes Routed from the End) Pipe Position and Relative Position Dimensions Unit: mm Building Scenario...
Water pipe routing (1) Condensate pan drainpipe (2) Evaporator condensate pan drainpipe (3) Floor drain pipe (4) Floor drain pipe (5) Water tank water refill pipe (6) Water tank drainpipe (7) Water trap...
Page 12
Sealing and Pipe Anti-freezing Protection Remove the paper protective Condensate drainpipes and water refill film from the sealing putty. pipes may freeze and thereby be blocked Seal the gaps between the or crack in low-temperature areas. Take water pipes and the equipment anti-freezing measures for the pipes.
Page 13
Installing an Air Deflector FDC Scenario Assemble an air deflector. Install the assembled air deflector on the corridor module. Building Scenario Assemble an air deflector. Install the assembled air deflector on the corridor module. Assembling the air deflector Assembling an air deflector (with an air damper) Installing an air deflector Installing the air deflector...
Installing Air Ducts 1. The customer needs to prepare air ducts based on the site requirements and install the prepared air ducts on the corresponding air vents. Unit: mm FDC Scenario Dimensions of Reserved Holes for Dimensions of Reserved Holes the Indoor Air Return Duct (End) for the Indoor Air Supply Duct Dimensions of Reserved Holes for...
• The example describes how to install an indoor air supply duct in the FDC scenario. • The entire air duct must be wrapped with thermal insulation foam. The thickness of the thermal insulation foam must be at least 3 cm. The joint between the air duct and the unit •...
Page 16
After power cables are correctly connected, use sealing putty to fill in the gaps between the cables and the cabinet. The sealing putty can be obtained from the fittings. (1) Paper protective film (2) Sealing putty (standard configuration) X501 X502 X504 X505 Smoke sensor power...
Page 17
(Optional) Connecting T/H Sensors Outside the Cabinet The T/H sensors outside the cabinet are used to detect the temperature and humidity of remote points. The installation position can be determined based on the site requirements. It is recommended that the sensors be deployed near heat sources, or near places that lack cooling capacity.
Page 18
(Optional) Connecting Motorized Dampers (Building Scenario) 1. Install the motorized damper at the air vent of the unit. 2. Install the cables. Connect one end of a cable to the X504 port, route the cable along the outside of the unit, and reserve the other end near the air damper actuator. Ensure that cable routing does not affect the maintenance of the unit.
Page 19
Name Description Running indicator Alarm indicator FE teamwork control FE_1 port CAN_IN port CAN teamwork and RS485 monitoring cascading RS485/12V port Connecting to T/H sensors USB port Connecting to a WiFi module or USB flash drive SW button Button for restoring factory settings FE teamwork control FE_2 port CAN_OUT port...
Page 20
Connect the COM/FE port on the main control module of the last smart cooling product in each group to the RS485 port on the host. CAN Teamwork + FE Monitoring Networking Teamwork Monitoring Protocol Modbus-TCP/SNMP Customers can purchase Huawei's switch and NetEco for the monitoring system.
Page 21
FE teamwork + FE monitoring Networking Teamwork Monitoring Protocol MCA_CAN Modbus-TCP/SNMP Customers can purchase Huawei's switch and NetEco for the monitoring system. FE Teamwork + RS485 Monitoring Networking Teamwork Monitoring Protocol MAC_CAN Modbus-RTU Connect the COM/FE port on the main control module of the last smart cooling product in each...
Removing the Transport Fasteners and Desiccant Bags from the Compressor Remove the sheet metal fasteners for securing the compressor during transportation. Find the desiccant bags in the compressor and electric control box and remove them. Verifying the Installation Check Item Check Content Result The unit installation meets the installation requirements.
Power-On Commissioning 11.1 Power-On Users are classified into two types: operator (preset password: 000001) and admin (preset password: 000001). After power-on, the device is in the shutdown state. After power-on, the compressor starts preheating, and the system generates a compressor ...
Page 24
Android currently. You must apply for the permission to use the app after downloading it. • During the commissioning of the smart cooling product, ensure that no comburent substance (such as air or additive) enters the smart cooling product system. Huawei is not liable for any risks and losses caused due to violation.
1. Initial Startup Flowchart 2. Wizard Startup Flowchart Start Start Tap Start on the home screen. Confirm precautions and check items. Tap Confirm, and the barcode and verification code are displayed. Select commissioning items. Open the Service Expert app. Failed Commission the indoor fan.
Page 26
Huawei Technologies Co., Ltd. Huawei Industrial Base, Bantian, Longgang Shenzhen 518129 People's Republic of China www.huawei.com...