Assembly
Step
Action
6
Screw the Duo-Taptite screw M8X25 (3) into the hole of the inner installation bracket (1) of the "left" housing (b).
Assembly work on GF units should begin with the heat recovery module.
7
Mount the modules in the corresponding assembly sequence (left housing in front of right housing!) on the ceilings
using installation brackets (1) and suitable mounting material (on-site sound decoupling). Observe the construction of
the units.
8
After the modules are mounted on the ceiling, press the modules into the click connectors by pressing them together. It
is important to ensure that the duo-taptite screw (3) is threaded into the slot of the "right housing" bracket (c).
Fig. 16 Connecting the equipotential bonding of the modules
1
Equipotential bonding symbol
2
Equipotential bonding screw
Step
Action
9
Establish equipotential bonding by connecting the modules using the equipotential bonding screw (2).
10
Then fit the covering cap (3).
11
Include the entire unit in the equipotential bonding.
3059570
To reduce the weight of the individual modules, the components can be removed from the
housing.
By means of the supplied special tool, the click connectors can be opened and removed from
the housing at any time after releasing the covering caps.
Subject to changes in line with technical progress.
NOTE
NOTE
1
3
Covering cap
2
3
29