COMMISSIONING

4.3.2 Installing the crane behind the cabin

* To the sides of the truck's subframe/frame bolt-on plates PL 10 (2) should be installed, with weld-
ed sleeves for stud bolts M30 (3).
- Follow the mounting instructions provided by the truck's manufacturer/importer
- Truck manufacturers do not recommend clamp mounting that would compress the frame beams
or welding directly to the frame beams.
* The crane (1) should be lifted on top of the mounting plates (2) (it should not remain upon the
frame beams) and the six M30 studs (3) should be installed to sleeves. The studs should be tight-
ened step by step with a torque wrench to 1.200 Nm (122 kpm).
* Install the grapple equipment: shackle (4), rotator (5), grapple (6) + hydraulic pipes, unless this
has not already been done at the factory.
* Connect the crane's return and pressure pipes to the truck's hydraulic system
At this stage a commissioning inspection has to be carried out.