Figure 69. Top cover installation
Step 1.
Align the posts inside the top cover with the slots on the chassis.
Step 2.
Hold the front of the server and slide the top cover towards the front server until it clicks into place.
After you install the top cover, complete the following steps:
1. Install the server into rack if necessary.
2. Reconnect power cords and all external cables.
3. Turn on the server (see "Power on the server" on page 80).

Install a hot-swap power supply unit

Use this information to install a hot-swap power supply unit.
To avoid possible danger, read and follow the following safety information.
S001
DANGER
Electrical current from power, telephone, and communication cables is hazardous.
To avoid a shock hazard:
• Connect all power cords to a properly wired and grounded electrical outlet/source.
• Connect any equipment that will be attached to this product to properly wired outlets/sources.
• When possible, use one hand only to connect or disconnect signal cables.
• Never turn on any equipment when there is evidence of fire, water, or structural damage.
• The device might have more than one power cord, to remove all electrical current from the
device, ensure that all power cords are disconnected from the power source.