FLOOR MOUNTED ACTIVE BEAM
INSTALLATION & MOUNTING INSTRUCTIONS
Utility Cabinet Installation for ACBC
Step 1: Determine utility cabinet
locations and orientation according to
approved plans.
Step 2: Secure blocking that runs
across the wall at the height of the
utility cabinet mounting brackets. The
blocking should be securely fastened
to the stud wall or similar structure.
Blocking and fasteners by others.
Step 3: Place the utility cabinet flush
against the wall and/or connecting
unit(s), pictured in Figure 22.
Step 4: Using the 4mm allen key open
the access door and turn both spring
latches to the left until access door is
opened, pictured in Figure 23. Remove
access door and place on a clean, flat
surface.
30
FLOOR MOUNTED ACTIVE BEAM - Manual | www.priceindustries.com
FIGURE 22
Figure 1
WALL
UTILITY CABINET
FIGURE 23
ROTATE LEFT
DETAIL A
A
WALL
ROTATE