Installation Instructions; Before You Start; Maintenance - Price ACBC Series Manual

Floor mounted active beam
Table of Contents

Advertisement

FLOOR MOUNTED ACTIVE BEAM
INSTALLATION & MOUNTING INSTRUCTIONS

Before You Start

Inspect all cartons and boxes for flaws and shipping damage.
If shipping damage has occurred, take photos and contact the
shipping company to file a freight claim immediately.
Ensure all tools (as listed on the following page) are on site and
ready for use.
A minimum of two (2) people are required for safe installation.
ACBC:
1 or 2 way discharge units
Vertical Coil
13.5 inch depth
60 to 87.438 inch length
Handling
Avoid introducing contaminants into the unit; such
as dust or dirt. Keep the induction grille face, the
duct inlet, and the water connection piping covered
at all times during the installation process.
To avoid smudging the unit while handling, the use
of clean white cotton gloves is recommended.
Storage of the units should be in a covered, dry
location while waiting for installation. Location should
be cleaned of excess dust before installation.
Typical installation on the floor
Determine where beams should be located using building
drawings and identification tags on schedule and units. Ensure
the beam's length, nozzle size, number of pipe connections,
pipe circuiting, duct size, duct inlet location and air discharge
configuration (1 way or 2 way) match the requirements
specified for that particular beam by cross referencing the Price
provided schedule, the order linestring and line instructions
with the units that are on site.
ACBC

Maintenance

Maintenance required is accessing the coil from the room side
through the removable face and vacuuming the water coil with
a soft bristle brush based on space and owner requirements.
Maintain water conditions which prevent corrosion of copper
tubing and ensure that safeguards against air accumulation
through leaks or oxygen diffusion in system piping are
functioning.
If included in the system design, check the condensate
sensor(s) or humidity sensor(s) according to sensor
manufacturer's methods and schedule.