Installing the Back Supply Plenum

Install the Supply Duct Collar

1. Find the center of the back supply plenum.
2. If the back supply plenum is to have
one opening, cut the opening such
that it is centered at L /2 from the
plenum end. (Fig. 1)
3. If the back supply plenum is to have
two openings, cut openings such
that they are centered at L /4 from
FIG. 12
each end of the plenum.
FIG. 9
(Fig. 2)
L (MODULE LENGTH)
4. Place the duct
L/2
collar(s) over the
L/2
opening(s), fastening
with screws or
tack-welds every
4 to 6 in. (10.16 to
15.24 cm). (Fig. 3)

Hang the Plenum

5. Hang the back
FIG. 13
supply plenum
FIG. 12
from the ceiling.
L (MODULE LENGTH)
The back supply plenum
L/2
FIG. 15
L/4
L (MODULE LENGTH)
needs to be mounted 31.25 in.
(79.375 cm) above the finished
L/2
floor. This is measured from the
lowest rear edge of the back
supply plenum to the finished
floor. (Fig. 4)
Hang using threaded rod
placed through the hanger brackets.
FIG. 15
FASTENERS HOLDING THE
BACKSUPPLY TO THE WALL
FASTENERS HOLDING THE
BACKSUPPLY TO THE WALL
Fig. 4
6. Fasten the back supply to the wall, going through the
lower back supply wall.
• These fasteners are to help maintain the location of
the back supply, and are not intended to hold the
FIG. 20
weight of the back supply unit.
31.25 INCH
FIG. 20
• The fasteners should not interfere with the
CRITICAL
DIMENSION
removable air diffusers.
1/4 INCH BOLT AND CAP NUT
SUPPLIED BY MANUFACTURER
FIG. 12
L (MODULE LENGTH)
L/2
FIG. 10
FIG. 13
Fig. 1
L/4
L (MODULE LENGTH)
L/2
FIG. 15
Fig. 2
FIG. 14
FIG. 13
L/4
L/2
L/4
Fig. 3
FASTENERS HOLDING THE
BACKSUPPLY TO THE WALL
FIG. 16
31.25 INCH
CRITICAL
DIMENSION
FIG. 20
31.25 INCH
CRITICAL
DIMENSION
HOLE DRILLED
BY INSTALLER
FULL END SKIRT
HOLE DRILLED
BY INSTALLER
ATTACH TO WALL
FASTENERS BY OTHERS
1/4 INCH BOLT AND CAP NUT
SUPPLIED BY MANUFACTURER

Ductwork

Exhaust
- As specified in NFPA 96, Ch. 7.5 (latest
edition), exhaust duct systems must be constructed in
the following manner:
Materials: Ducts shall be constructed of and supported
by carbon steel not less than 1.37 mm (0.054 in.) (No.
L/2
16 MSG) in thickness, or stainless steel not less than
1.09 mm (0.043 in.) (No. 18 MSG) in thickness.
Installation: All seams, joints, penetrations, and duct to
hood collar connections shall have a liquid-tight external
weld. If you have an automatic fire damper, please refer
FIG. 14
FIG. 10
to that manual for installation instructions now.
For hoods with fire dampers in the exhaust and
supply duct collars, an access panel for cleaning and
L/4
inspection shall be provided in the duct. This panel
shall be as close to the hood as possible but should
not exceed 18 in. (45.72 cm).
Supply
- Supply ductwork (where applicable) should
be connected to the hood in a manner approved by the
local code authorities.
FIG. 14
For proper installation of duct collars when they are
shipped unattached, see page 8.
L (MODULE LENGTH)
L/2
L/4

Continuous Capture Plenum Hoods

FIG. 16
1. Remove the support angles
provided for support during
shipping on the open
end panels. Install
and level both
hoods.
DIMENSION
FIG. 16
2. After leveling, secure the
hoods together by tack-
welding and/or bolting the
angles that are located at
the top of the hoods along
HOLE DRILLED
BY INSTALLER
REMOVE
its width (Fig. 5).
SUPPORT
ANGLES ON
THE OPEN
3. Next, fasten the hoods
END PANEL
together at its inside
1/4 INCH BOLT AND CAP NUT
SUPPLIED BY MANUFACTURER
plenum profile using
u-clips and bolts (Fig. 6).
Caulk this joint with NSF
FIG. 23
Approved silicone caulk
(GE SCS1009 or its
FIG. 23
equivalent). The caulk is
not provided.
HOOD END PANEL
HOOD END PANEL
HEMMED EDGE
FIG. 13
L/4
L (MODULE LENGTH)
L/2
L/4
NOTE
31.25 INCH
CRITICAL
REMOVE
SUPPORT
ANGLES ON
THE OPEN
END PANEL
CAULK
BOLT
SUPPORT ANGLES
1. REMOVE SUPPORT ANGLE ON OPEN END PANEL.
2. RAISE ALL HOODS INTO APPROPRIATE LOCATION
AND SUPPORT PER CONSTRUCTION PLANS.
3. FASTEN TOP ANGLES TOGETHER USING 1/4 in. BOLTS & NUTS (BY OTHERS).
4. FASTEN HOODS TOGETHER USING U-CLIPS, 1/4 in. BOLTS
& CAP NUTS AS INDICATED.
CAULK
5. CAULK ALL SEAMS AS NECESSARY.
BOLT
HOOD FRONT PANEL
HOOD FRONT PANEL
SUPPORT ANGLES
Kitchen Hoods • Type I and Type II
FIG. 14
FIG. 16
CAULK
SUPPORT A
HOOD
1. REMOVE SUPPORT ANGLE ON OPEN END
2. RAISE ALL HOODS INTO APPROPRIATE LO
ACORN
FIG. 17
AND SUPPORT PER CONSTRUCTION PLAN
NUT
3. FASTEN TOP ANGLES TOGETHER USING 1
U-CLIP
4. FASTEN HOODS TOGETHER USING U-CLIP
& CAP NUTS AS INDICATED.
Fig. 5
5. CAULK ALL SEAMS AS NECESSARY.
BOLT OR WELD
FIG. 23
HOOD TOP
HOOD END
HOOD END PANEL
Fig. 6
HOOD
ACORN
NUT
FIG. 53
U-CLIP
SLIDE FLANGE
BEHIND BACK
OF THE HOOD
REMOVA
BOLT OR WELD
9
BOLT
HOO
HO
FIG