3. Main Technical Mechanism Parameters Table
Name
Max. lifting height
Working
temperature
Working environment
4.
Packing, transport and storage
Only skilled personnel who are familiar with the lift and this manual shall be allowed
to carry out packing, lifting, handling, transport and unpacking operations.
4.1 Packing
90% components were pre-assembled before shipment, and packed with blister packing in
steel frame. Arms, adapters and rubber pads were put in the lift. Power unit was packed in
carton box separately, power unit stand was packed and fixed on above the lifts.
4.2 Lifting and handling
When loading/unloading or transporting the equipment to the site, be sure to use suitable
Model
Lifting capacity:
Lifting speed
Weight
Noise
environment
Power
Working voltage of
control system
Voltage
Safety catch
Movable QJY-2.5-H
2500kg
1800 mm
24mm/s
750kg
<70 dB
-5 ℃/+40℃
Indoors
1.5kw
24V
110V/220V/380V/415V
Manual
5