GSI Group SCR Series Instruction Manual

GSI Group SCR Series Instruction Manual

Drive board

Advertisement

Network Series SCR
Board Setup Instructions
Instruction
Manual
PNEG-1346
Date: 9-14-2006
PNEG-1346

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the SCR Series and is the answer not in the manual?

Questions and answers

Summary of Contents for GSI Group SCR Series

  • Page 1 Network Series SCR Board Setup Instructions Instruction Manual PNEG-1346 Date: 9-14-2006 PNEG-1346...
  • Page 2 It is relatively easy to calibrate the SCR Drive Board and is something that should be checked periodically, particularly before the start of the drying season and also as a preventive measure. There are four settings on the SCR Drive Board: IR - IR compensation.
  • Page 3 SCR board terminals and min./max. adjustment locations. * Terminals L1 and L2 are the input terminals. When the un- load system is turned on there should be 220 Volts AC across these terminals. * Terminals A+ and A- are the output terminals.
  • Page 4 Control panel switch locations. Unload Moisture Control Switch Switch Drying Mode Switch Meter Roll Speed Control Potentiometer Before starting the procedure set the dryer up as follows: 1. All fan and heater switches to off position and load switch to off position. 2.
  • Page 5 2. Switch the Moisture Control Switch to the off position. This will put the meter roll rotation speed at the high setting. 3. Use a voltmeter set at the 200 volt DC range and probe terminal A+ with the red voltmeter probe and A- with the black voltmeter probe.
  • Page 6 Authorities having jurisdiction should be consulted before installation occurs. The GSI Group, Inc. 1004 E. Illinois St. Assumption, IL 62510-0020 Phone: 217-226-4421 Fax: 217-226-4420 e-mail: gsisales@grainsystems.com internet: http://www.grainsystems.com Copyright © 2006 by The GSI Group Printed in the USA...

Table of Contents