2.16 Next Steps

Once the unit is physically installed per the instructions above, the next steps are:
Optionally, implement the onAER option, which allows your unit to be monitored
remotely. To implement this option, complete the instructions in the next section, onAER
Setup.
Start the unit for the first time and perform the combustion calibration procedure. For
instructions, see the Benchmark-Edge [i] Operation and Service Manual, OMM-0137
(GF-210), Section 4: Initial Startup.