Mechanical Backup Bin Control Check - Hoshizaki FD-1001MAJ-C Instruction Manual

Modular flaker
Table of Contents

Advertisement

2. Mechanical Backup Bin Control Check

1) Make sure the power switch is in the "OFF" position and that the power supply is off.
2) Remove the top panel.
3) Remove the strap connecting the spout to the chute assembly. See Fig. 20. Pull up the
chute assembly slightly so that you can access the actuator located in the top of the
chute.
4) Turn on the power supply. Make sure the control switch is in the "ICE" position, then
move the power switch to the "ON" position.
Chute Assembly
Strap
5) 30 seconds after the upper float switch closes, the control board "GM" LED turns on.
After "GM" LED turns on, press the "SERVICE" button on the control board to bypass
the 5-minute compressor delay. WARNING! Risk of electric shock. Care should be
taken not to touch live terminals.
6) "GM" LED and "COMP" LED are on. Press the actuator located in the top of the chute.
"COMP" LED and "GM" LED turn off within 10 seconds and the control board sounds a
9 beep alarm. Release the actuator.
7) Move the power switch to the "OFF" position, then turn off the power supply.
Note: The control board alarm resets when power is turned off.
8) Replace the chute assembly and strap in their correct positions.
9) Replace the control box cover and top panel in their correct positions.
10) Turn on the power supply. Make sure the control switch is in the "ICE" position, then
move the power switch to the "ON" position to start the automatic icemaking process.
11) Replace the front panel in its correct position.
Strap
Model Shown: F-1501MRH-C
37
Proximity Switch
Actuator
Spout
Fig. 20

Advertisement

Table of Contents
loading

Table of Contents