Operation

Operation
Operation
Pressure Relief
Relief Procedure
Procedure
Pressure
Pressure
Relief
Procedure
Follow the Pressure Relief Procedure
whenever you see this symbol.
This equipment stays pressurized until pressure
is manually relieved. To help prevent serious
injury from pressurized fluid such as splashing
fluid and moving parts, follow the Pressure Relief
Procedure before cleaning, checking, or servicing
the equipment.
1. Close the agitator shut-off valve.
2. Shut off the air supply to any accessories such
as feed pumps or an elevator.
Ref.
Ref.
Ref.
Description
Description
Description
AR
Air Restrictor (Elevator Speed)
EC
Elevator Control Selector
AS
Agitator Shut Off Valve
FP
Feed Pump Shut Off Valve
SA
Supply Air Inlet
LB
Agitator Lubricator
RG
Agitator Regulator and Gauge
3A4032B

Setup

Setup
Setup
To reduce the risk of serious injury from moving
parts and splashing fluid, always shut off the
agitator before you raise, check, or repair the
agitator.
1. Before turning on supply air, make sure all valves
are in the CLOSED or OFF position.
a. For elevator packages, make sure that
the elevator control selector is in the OFF
position.
b. Make sure that the agitator shut-off valve is
CLOSED.
c. If using a feed pump, make sure that the
pump shut-off valve is CLOSED.
2. Turn on the air supply to the system.