To connect the drain piping to the indoor unit
FCAG35~140BVEB
Split system air conditioners
4P561448-1B – 2021.07
1~1.5 m
a Hanging bar
O Allowed
X Not allowed
Rising piping. If necessary to make the slope possible, you can install rising
piping.
-
Drain hose inclination: 0~75 mm to avoid stress on the piping and to avoid air
bubbles.
-
Rising piping: ≤300 mm from the unit, ≤675 mm perpendicular to the unit.
a
b
a Metal clamp (accessory)
b Drain hose (accessory)
c Rising drain piping (vinyl pipe of 25 mm nominal diameter and 32 mm outer
diameter) (field supply)
d Hanging bars (field supply)
Condensation. Take measures against condensation. Insulate the complete drain
piping in the building.
Combining drain pipes. You can combine drain pipes. Make sure to use drain
pipes and T-joints with a correct gauge for the operating capacity of the units.
a T-joint
NOTICE
Incorrect connection of the drain hose might cause leaks, and damage the
installation space and surroundings.
1 Push the drain hose as far as possible over the drain pipe connection.
2 Tighten the metal clamp until the screw head is less than 4  mm from the
metal clamp part.
3 Check for water leaks (see
4 Install the insulation piece (drain pipe).
a
≤300
1000~1500
a
b
c
d
d
a
"To check for water
6
Installation
|
(mm)
(mm)
4
leaks" [
 34]).