Bill of Materials
1.4 Bill of Materials
Table 1–2 lists materials required for the SLVP191
Table 1–1. SLVP191 Bill of Materials
Ref
79301
79328
Des
Description
Capacitor, ceramic, 1.0 µF, 6.3 V,
1
1
C1
10%
Capacitor, ceramic, 0.0047 µF, . . .
1
1
C2
25 V, X7R, 10%
Capacitor, ceramic, 4.7 µF, 16 V,
1
1
C3
X5R, 15%
1
C4
Capacitor, ceramic, 100 pF, 50 V,
C0G, 5%
0
Not used
1
1
J1
Clip, surface-mount, 0.040 board,
0.090 standoff
1
1
J2
Clip, surface-mount, 0.040 board,
0.090 standoff
1
1
J3
Clip, surface-mount, 0.040 board,
0.090 standoff
1
1
J4
Clip, surface-mount, 0.040 board,
0.090 standoff
1
1
R1
Resistor, chip, 10 kΩ, 1/16 W, 1%
0
0
R2
Not used
1
R3
Resistor, chip, 30.1 kΩ,, 1/16 W,
1%
0
Not used
1
R4
Resistor, chip, 6.8 kΩ,, 1/16 W, 1%
0
Not used
1
U1
IC, high PSRR, low noise LDO, adj
output, 100 mA
1
IC, high PSRR, low noise LDO,
2.8 V, 200 mA
PCB, 0.705 in × 0.570 in × 0.031
1
1
1-4
Size
MFR
Part Number
603
Murata
GRM39X7R105K6.3
603
Murata
GRM39X7R472K25
1206
Murata
GRM42–6X5R475K16
603
Murata
GRM39C0G101J50
0.100"
NAS Interplex
CA26DA–D36W–0FC
0.100"
NAS Interplex
CA26DA–D36W–0FC
0.100"
NAS Interplex
CA26DA–D36W–0FC
0.100"
NAS Interplex
CA26DA–D36W–0FC
603
Std
Std
603
Std
Std
603
Std
Std
SOT23–6
TI
TPS79301DBV
SOT23–5
TI
TPS79328DBV
Any
SLVP191