6.9. Power limitation and protection configuration

To configure the safety protections and operating range limitations of the supervisor access the INSTALLER MENU (press [Prg]+[Esc]
and enter the installer password PW1) ->CONFIGURATION -> PROTECTIONS.
1.
On the PUMPS LIMITATION screens, adjust the percentages of maximum and minimum of pump circulations during
operation of the heat pump.
2.
On the BRINE ALARM screen set the minimum temperature of the brine circuit below which the alarm is activated and
the heat pump turns off.
3.
On the COOLING ALARM screen set the minimum outlet temperature during operation of the heat pump in COOLING
mode below which the alarm is activated and the heat pump turns off.
4.
To configure power limitation and protection configuration in heat pump connected to supervisor see Installation and
operating manual ecoGEO HP.

6.10. Final inspection and commissioning

Commissioning should be performed only after verification that all the circuits have been properly
filled and bled.
NOTE
Before commissioning, check that all the pumps, valves and other components are functioning
correctly. To do this, you can enable them individually in the installer menu → manual activation of
components.
Before commissioning, check that all the circuits are flowing and that nothing is preventing the flow.
Check the following points to ensure that they have been carried out successfully.
Inspection of the electrical installation:
1.
The power supply has been connected to the terminal block of the supervisor in accordance with the instructions in
section 4.2.
2.
The pLAN bus communication cable has been connected between the supervisor and the rest of the pLAN network
(ecoGEO HP heat pumps, Supervisor module, etc.) in accordance with the instructions in section 4.3. For more
information, refer to the ecoGEO HP heat pump and Supervisor module manuals.
3.
All the temperature probes required for the supervisor, the ecoGEO HP heat pumps and, if there is one, the Supervisor
module have been installed, in accordance with the instructions in sections 4.1. For more information, refer to the
ecoGEO HP heat pump manuals.
4.
All the control signals from external equipment (thermostats and/or other external equipment) have been connected to
the supervisor, the ecoGEO HP heat pumps and, if there is one, the Supervisor module, in accordance with the
instructions in sections 4.1. For more information, refer to the ecoGEO HP heat pump manuals.
5.
All the external equipment (pumps, valves and/or other external equipment) have been connected to the supervisor, the
ecoGEO HP heat pumps and, if there is one, the Supervisor module, in accordance with the instructions in sections 4.1.
For more information, refer to the ecoGEO HP heat pump manuals.