3.
Align the inner rails you installed on the sides of the system with the open por-
tion of the slide assemblies (see Figure 1-19).
4.
Push the system into the slide assemblies until the system stops (see
Figure 1-19).

Figure 1-19. Installing the System in the Rack

5.
Press in on the release latch on each extended slide and push the chassis into the
rack.
6.
Tighten the captive thumbscrews on each side of the front chassis panel to
secure the system to the rack.

Installing the Cable-Management Arm

To install the cable-management arm on the back of the system, perform the follow-
ing steps:
1.
Facing the back of the rack cabinet, locate the threaded hole on the back of the
slide assembly and secure the end of the cable-management arm (the end having
a bracket and captive thumbscrew) to the right side vertical rail (see Figure 1-20).
The bracket snaps into the square mounting holes on the vertical rail and is
secured with a captive thumbscrew.
inner rail
captive thumbscrews (2)