  Step 3: Verifying Proper Activation and Commissioning
Power Control
Power control options are detailed in the Power Control Application
Note , available on the SolarEdge website at
https://www.solaredge.com/sites/default/files/application_note_power_
control_configuration.pdf.
The Grid Control option may be disabled. Enabling it opens additional
options in the menu.
The Energy Manager option is used for setting power export limitation, as
described in the Export Limitation Application Note , available on the
SolarEdge website at
in_limitation_application_note.pdf.
 
Step 3: Verifying Proper Activation and
Commissioning
 1. Select Information and verify that the correct firmware versions are installed on each
inverter.
 2. Select Status and verify that inverter is operating and producing power.
 3. Verify that additional configurations were properly set by viewing the relevant
Status screens.
 4. Verify that the green inverter LED is steadily lit.
Your SolarEdge power harvesting system is now operational.

Reporting and Monitoring Installation Data

Monitoring the site requires connecting the inverter to the monitoring platform, using
any of the wired or wireless options available from SolarEdge. Refer to Setting Up
Communication to the Monitoring Platform on page 39.
The Monitoring Platform
The monitoring platform provides enhanced PV performance monitoring and yield
assurance through immediate fault detection and alerts at the module, string and
system level.
https://www.solaredge.com/sites/default/files/feed-
Three Phase System MAN-01-00505-1.5