3. Make sure only one Zigbee device is powered up right now: the Zigbee to USB converter connected
to the CCGX. Power down all others. If you don't do this, the Zigbee to RS485 converter may be
connected permanently to another Zigbee device.
4. Connect the 12V DC power supply to the Zigbee to RS485 converter. When the power is switched
on, check the LEDs again.
Option B: Wired connection to CCGX
Connect the meter to the CCGX using the USB to RS485 converter cable:
RS485 Converter Grid meter
Yellow
Terminal 41
Orange
Terminal 42
Black
Terminal 43
The Red, Green and Brown wire are not used
5. Multi/Quattro installation and configuration
First, follow the instructions as per the standard installation manual. AC Input 1 is connected to the
distribution panel of the installation. And, optionally, AC Output 1 can be used as a UPS output: in the
event of a grid failure, the built-in inverter will power loads connected to AC Output 1.
Then use VEConfigure3 to
If you have a Multi Compact, check the DIP switches: DIP switch 1 must be on, and DIP switch 2 must
be off.
If you used an earlier (beta) version of the assistant, make sure to remove it from the 'private
assistant directory' in VE configure, or disable the directory. You can set the private directory in the
'Assistant Tools' tab within the 'Assistants' tab.
https://www.victronenergy.com/live/
load the assistant
'self consumption Hub-4' into the device.