Post Installation Verification and Configuration
Use the checklist below to verify that the system is properly connected and configured.

Installation and Wiring

1.
Make sure the distances between the system components are as specified in the installation guide.
2.
Take a picture of each of the system components after wiring them and send the pictures to SolarEdge support.
Inverter
StorEdge Interface
Battery
Energy Meter
3.
Make sure the battery splash cover is closed.
4.
Make sure the DIP switches of all components are set as shown in the connection diagram.
5.
Make sure all DC, communication and AC cabling connections are completed as follows:
Check the AC wiring and the AC circuit breaker on the AC distribution panel.
Check the string DC input voltage. Expect 1V per optimizer in a string.
Make sure all components are properly grounded.
Check the DC connections on the battery and StorEdge Interface.
Check the RS485 connection between the battery and inverter.
Check the CT, AC and RS485 connections to the Energy Meter.
6.
Check connection to Monitoring Platform:
In SetApp, select Commissioning > Status.
Check that S_OK - Server Connected appears in the main inverter section.
Configuring the Battery and Meter
1.
Switch the inverter ON/OFF/P switch to OFF.
2.
Access SetApp and select Commissioning > Communication.
3.
From the Communication screen, select RS485-1 > Protocol > Modbus (Multi-Device).
4.
Return to the previous screen and select Add Modbus Device > Battery.
5.
Verify the battery information by selecting Battery 1 > Battery Information.
6.
In the RS485-1 screen, select Add Modbus Device > Meter.
7.
Set the meter's CT Rating according to the CT specifications. If the CT rating value returns to 0, check
communication with the CT.
8.
Select Meter 1 > Meter Function > Export+Import (E+I).
MAN-01-00642-1.1 StorEdge Single Phase Inverter Wiring and On Site Check Quick Guide
Post Installation Verification and Configuration