6.3 Powering On the System

Prerequisites
You have put on insulation gloves.
Procedure
Step 1 Switch circuit breaker QF13 on the AC output side to ON.
Step 2 Switch circuit breakers QF01 to QF12 on the AC input side to ON one by one.
Step 3 Switch circuit breaker QF14 in the monitoring compartment to ON.
----End

6.4 Powering Off the System

Prerequisites
You have put on insulation gloves.
Procedure
Step 1 Switch circuit breaker QF14 in the monitoring compartment to OFF.
Step 2 Switch circuit breakers QF01 to QF12 on the AC input side to OFF one by one.
Step 3 Switch circuit breaker QF13 on the AC output side to OFF.
----End