d . When control power is restored, lift the
push button protective cover of the Mark VI
CS-1A Switch Operator .
e . Then press the "OPEN" push button, located
on the front of the Mark VI CS-1A Switch
Operator, for about one second, or send a
remote trip signal to the operator . See Fig-
ure 20 . The disconnect will open, and the
charging motors will begin charg ing the
interrupters . Charging takes approximately
two minutes .
"OPEN" push button
Figure 20. Push the local-trip push button or send a user-furnished
"OPEN" signal.
Switch Operation
S&C Instruction Sheet 712-501
17