o Cable routes shall be guarded by use of railings, industrial safety gates, floor hole
covers or toe-boards
o Minimal passing between items shall take place once initial setup is complete.
Launch pads can be directly next to each other.
Continuous monitoring and event reporting shall be implemented and conducted
A Battery Maintenance Plan shall be implemented and adhered to
Replace all mechanical parts that have been damaged or have been subject to known
over load
Safety Audits shall be conducted
Operation
Operational safety and safety of work training is mandatory
o Crew shall be trained to perform typical tasks and to operate safely
o Safety Briefing and safety training is mandatory
o If interacting with performers a choreography shall be developed and trained,
and rehearsals shall be conducted
Regular inspection before commission according to checklist shall be conducted and
documented
Geo fence to terminate flight within pre-defined safety area must be defined and
implemented.
Limit operational altitude to 50m AGL; implement 1:1 rule to audience when flying more
than 50m AGL
Operations shall be suspended when adequate level of safety cannot be maintained
If required due to an inability to control environmental conditions, enforcement of
safety area with restricted access (here: crew only; no exposure to third party) shall be
conducted
Avoid passing between items on the ground