Installing Cables - Huawei DPU40D-N06A3 Quick Manual

Distributed power
Hide thumbs Also See for DPU40D-N06A3:

Advertisement

4.8
Flush Mounting on Channel or Angle Steel
Channel steel
size and
installation
method
Angle steel
size and
installation
method
5

Installing Cables

5.1
Installing a Ground Cable
NOTE
The following figure uses one
PSU and one lithium battery as
an example.
5.2
Preparing AC and DC Cables
DC wiring terminal
Negative (blue)
Positive (red)
PSU load cables and AC input cables should be prepared onsite. DC load cables are used as an example here. Refer to this proc edure
when preparing AC cables.
Multi-core cables should be used as AC and DC power cables; otherwise, water may seep into the waterproof connectors.
Before assembling the waterproof connector, check whether the connection between the cable and terminal is firm and reliable.
Preparing DC Cables and Connecting Waterproof Connectors
If the cable diameter is ≤ 6 mm
Core cross-sectional area: 10 mm²
Lithium battery
AC wiring terminal
PE (green)
N/L2/HVDC negative (blue)
L/L1/HVDC positive (brown)
2
, prepare cables as follows:
(Unit: mm)
PSU
Cable Type
AC (3-core)
DC (2-core)
6
As shown in the left figures, when
the narrow edge size of channel
steel is less than 40 mm, only
installation methods a and b are
supported.
When channel or angle steel is
used for installation, each layer
supports a maximum of 1 PSU + 1
lithium battery or 2 PSUs. Refer to
the procedure for flush mounting
on a small pole.
Site ground bar
Core cross-sectional
area: 16 mm²
Core Cross-
Cable Outer
Sectional Area
Diameter
2
2–4 mm
9.0–14.5 mm
2
3.3–6 mm
(O-type
DC power cable)
2
4–10 mm
(D-type
DC power cable)
Scale line

Advertisement

loading