BEFORE YOU START PLEASE READ INSTRUCTIONS CAREFULLY
- Check the pack and make sure you have all the parts listed.
- When you are ready to start, make sure you have the right tools at hand (not supplied)
including a Phillips screwdriver, Stanley knife, wood saw, step ladder and drill with 2mm
bit.
- Ensure there is plenty of space and a clean dry area for assembly.
TIMBER
As with all natural materials, timber can be a ected during various weather conditions.
For the duration of heavy or extended periods of rain, swelling of the wood panels may
occur. Warping of the wood may also occur during excessive dry spells due to an interior
moisture loss. Unfortunately, these processes cannot be avoided but can be helped. It is
suggested that the outdoor building is sprayed with water during extended periods of
warm sunshine and sheltered as much as possible during rain or snow.
Our buildings are pre treated with a water based treatment**; this only helps to protect
the product during transit and for upto 3 months against mould. To validate your
guarantee and ensure longevity of the product, it is ESSENTIAL the building is treated
with a wood preserver within the rst three months of assembly and thereafter in
accordance with the manufactures recommendations. Care must be taken to ensure
the product is placed on a suitable base.
BUILDING A BASE
When thinking about where the building and base is going to be constructed:
Ensure that there will be access to all sides for maintenance work and annual
treatment.
Ensure the base is level and is built on rm ground, to prevent distortion. Refer to
diagrams for the base dimensions, The base should be slightly smaller than the external
measurement of the building, i.e. The cladding should overlap the base, creating a run
o for water. It is also recommended that the oor be at least 25mm above the
surrounding ground level to avoid ooding.
TYPES OF BASE
- Concrete 75mm laid on top of 75mm hard-core.
- Slabs laid on 50mm of sharp sand.
Whilst all products manufactured are made to the highest standards of Safety and in
the case of childrens products independently tested to EN71 level, we cannot accept
responsibility for your safety whilst erecting or using this product.
Refer to the instructions pages for you speci c product code
Please retain product label and instructions for future reference
x2
All building's should be
erected by two adults
For ease of assembly, you
MUST pilot drill all screw
holes and ensure all screw
heads are countersunk.
2mm Drill bit
**Protim Aquatan T5 (621)**
Your building has been treated with Aquatan.
Aquatan is a water-based concentrate which is diluted with water, the building as been treated by the correct
application of Aquatan solution and then allowed to dry.
Aquatan is a decorative nish to colour the wood, which is applied industrially to timber fence panels and
garden buildings.
Aquatan undiluted contains: boric acid, sodium hydroxide 32% solution, aqueos mixture of sodium dioctyl
sulphosuccinat and alcohols: 2, 4, 6-trichlorophenol.
For assistance please contact customer care on: 01636 880514
Mercia Garden Products Limited,
Sutton On Trent,
Newark,
Nottinghamshire,
NG23 6QN
www.merciagardenproducts.co.uk
Winter = High Moisture = Expansion
Summer = Low Moisture = Contraction
CAUTION
Every e ort has been made during the
manufacturing process to eliminate the
prospect of splinters on rough surfaces of the
timber. You are strongly advised to wear gloves
when working with or handling rough sawn
timber.

Advertisement

loading
Need help?

Need help?

Do you have a question about the 01SHPWOR1010DDOW-V2 and is the answer not in the manual?

Questions and answers

Summary of Contents for Mercia Garden Products 01SHPWOR1010DDOW-V2

  • Page 1 For assistance please contact customer care on: 01636 880514 - Concrete 75mm laid on top of 75mm hard-core. - Slabs laid on 50mm of sharp sand. Mercia Garden Products Limited, Sutton On Trent, Whilst all products manufactured are made to the highest standards of Safety and in...
  • Page 2: Pre-Assembly

    H=220cm W=140cm L=130cm 01SHPWOR1010DDOW-V2 Please retain product label and instructions for future reference Overall Dimensions: Nail Bag Length = 3114mm 30mm Screw x 91 Felt Tacks x 170 Width = 3179mm 40mm Screw x 106 Height = 2485mm 16mm Screws x 12...
  • Page 3 Step 2 Step 3 Plain Gable Assembly Lay the Front Gable Left next to the Front Lay the Back Left Gable and Back Right Top Gable, ensure they are level at the top Gable on a level oor place them next to then x together using 2x50mm screws.
  • Page 4 Step 4 Step 5 Place oor on rm and level base, ensure Fix the corners with 50mm base has suitable drainage free from areas screws as shown in diagram. where water can collect. (See front page on base requirements). Do not secure the building to the oor until the roof is tted.
  • Page 5 Step 9 Step 7 Fit the Door Gable Rail between the Fix the remaining plain side with Front Gable Left and Right. Fix to 50mm screws as shown in diagram. the oor using 3x50mm screws. Ensure screws line up with the 3x50mm Screws framing.
  • Page 6 Step 10 Step 11 Place a Truss central to where two Using x3 strips (No. 20) cut two trims at 1783mm and panels join. Align the top of the one strip at 1445mm. truss with the top of the sides as shown in the diagram.
  • Page 7 Step 13 Step 12 Place the second roof sheet Place a roof sheet ontop of the ontop of the truss and ensure plain gable and truss making sure that it butts up to the one the roof sheet sits into the gables and x using 40mm screws.
  • Page 8 Step 15 Step 14 Cut four strips of felt and place Once the roof is xed onto the roof. See below for attatch the building to the sizes. oor with 50 mm screws. Place the felt at onto the roof 36 x 50mm Screws in the order that is stated on the diagram below.
  • Page 9 Step 17 Step 16 Fit the fascias to the roof Fit the cover trims to the over the felt and secure in building and secure in place place with 40mm screws as with 40mm screws as shown. shown. Fit the Plain Gable Strip Pre drill to avoid splitting.
  • Page 10 Step 18 Step 19 *SCREW COUNT PER WINDOW Place the cover strip 11mm above the window gap in the window panel and Place the Cloaking Strip to the x with 3x30mm screws per strip. rear of one of the doors. Fixing in 30mm position screwing through the door Measure and trim before tting.
  • Page 11 Step 21 Step 20 Fix the casement stay to the opening window then align the xings onto the window panel frame. Ensure the case- To x the lock in place. Screw the Staple ment stay ts into xings when to the Door Gable or Slave door. closed before screwing them down using 12 x 20mm screws.
  • Page 12: After Treatment

    AFTER TREATMENT: score around protective cover on glazing and carefuly peel covering back It is ESSENTIAL that you apply wood treatment immediately after the building has been assembled. P 12...