Sample cooler type
ƒ DTC-DCCP
Cooler cooling water connections
ƒ 1/4 inch tube fitting
Cooling water consumption
ƒ 0.2 gpm (0.8 Lpm) at 22°C (71.6°F)
Input power
ƒ DCCP-x1xxx: 110–120 VAC, 1 phase, 50/60 Hz
ƒ DCCP-x2xxx: 220–240 VAC, 1 phase, 50/60 Hz
Power consumption
ƒ 1.6 KVA
Cell holders (optional)
ƒ 3/4 inch FNPT, 316 SS
Resin column (optional)
ƒ Sentry RC-100
Indoor/outdoor use
ƒ Altitude: Up to 6,561 ft (2,000 m)
ƒ Ambient temperature: 36°F to 122°F (2°C to 50°C)
ƒ Relative humidity: 0% to 85% RH
ƒ Pollution degree 2
ƒ Overvoltage Category II
ƒ Main supply voltage fluctuations up to ±10% of the nominal voltage

Installation

Sharp Edges! Wear gloves when lifting and carrying the panel as edges could be sharp .
To ensure proper alignment and safe installation, lifting and carrying should be completed by at
least two people .
This instrument should be installed by qualified technical personnel to ensure adherence to all
applicable codes .
Use proper connection sizing to avoid an unsafe condition . This product comes standard with
1/4" compression fittings for the sample inlet/outlet, and 1/4" compression connections for the
cooling water inlet/outlet . Never attempt to install a metric equivalent tube, pipe, or fittings into
these connection points .
Lift unit by the stainless steel backplate . Do not lift using mounted components as these could
break, damaging the equipment and possibly causing personal injury .