Rice Lake RoughDeck CS Operator's & Installation Manual

Rice Lake RoughDeck CS Operator's & Installation Manual

Coil scale
Hide thumbs Also See for RoughDeck CS:

Advertisement

Quick Links

RoughDeck CS
®
Coil Scale
Operator Installation Manual
114975 Rev B

Advertisement

Table of Contents
loading

Summary of Contents for Rice Lake RoughDeck CS

  • Page 1 RoughDeck CS ® Coil Scale Operator Installation Manual 114975 Rev B...
  • Page 3: Table Of Contents

    Visit www.ricelake.com/webinars. or obtained by calling 715-234-9171 and asking for the training department. © 2010 Rice Lake Weighing Systems. All rights reserved. Printed in the United States of America. Specifications subject to change without notice.
  • Page 4 Technical training seminars are available through Rice Lake Weighing Systems. Course descriptions and dates can be viewed at www.ricelake.com/training or obtained by calling 715-234-9171 and asking for the training department. RoughDeck® CS Operator Installation Manual...
  • Page 5: Installation

    Introduction This manual is intended for use by technicians responsible for installing and servicing the RoughDeck ® Authorized distributors and their employees can view or download this manual from the Rice Lake Weighing Systems distributor site at www.ricelake.com Site Consideration: The opening of the V-Top coil cradle option runs parallel with the load cell pocket CAUTION cover plate.
  • Page 6: Temporary Setting Blocks

    Temporary Setting Blocks Most installers use setting blocks that are approximately 3" high for the initial placement and connecting of the deck module. Use leveling bolts in base plate to level the scale. Setting blocks are only used in the corners of the module where the load cell mounts are installed.
  • Page 7: Load Cell Mount Installation

    Load Cell Mount Installation Load cell mount components (baseplate, mount blocks, anchor bolts, link, load cell, and upper mount blocks) are shipped in the hardware box and need to be assembled while in the load cell pocket. Remove the printed load cell Certificate of Conformance (CC) forms (included with load cells) and store them in a safe place for future reference.
  • Page 8 Figure 2-3. V-Top coil cradle option showing orientation 9. Adjust leveling bolts until radius of block comes in contact with rocker link radius. 10. Jack the weigh module and remove setting blocks. 11. Slowly lower the weigh module until it rests on the load cell links. After the weigh module is lowered into final position, check each load cell mount assembly to ensure that the link is plumb and that there is no binding or misalignment.
  • Page 9: Load Cell Wiring

    Load Cell Wiring Before the weigh module wiring can be completed, all load cell cables have to be routed through the conduit beginning at the load cell outlet. Use the following steps to route load cell cables through conduit to the J-box: 1.
  • Page 10: Trimming & Calibration

    Drip Loop Figure 3-2. Load Cell Wiring Drawing Load Cell Wire Color Function + EXC Black - EXC Green + SIG White - SIG Gray or Bare Shield Table 3-1. Load Cell Wiring Trimming & Calibration Refer to the JB4SS TuffSeal™ Signal Trim Junction Box manual for trimming details. Refer to indicator manual for connection and calibration details.
  • Page 11: Load Cell Replacement

    Load Cell Replacement Use the following steps to replace load cells in the RoughDeck® CS coil scale: 1. Position jack on the concrete Load Cell Bolts foundation beneath one of the weighbridge’s main frame members close to the load cell mount. (Allow Upper Mount room for load cell removal and Block...
  • Page 12: Troubleshooting

    Troubleshooting If the system powers up and gives some type of stable digital readout that varies with the load on the system, any system problems are probably caused by factors other than the load cells. The load cells are often blamed for a malfunctioning system, but the majority of the time, the problem lies elsewhere.
  • Page 13 RoughDeck Limited Warranty Rice Lake Weighing Systems (RLWS) warrants that all RLWS equipment and systems properly installed by a Distributor or Original Equipment Manufacturer (OEM) will operate per written specifications as confirmed by the Distributor/OEM and accepted by RLWS. RoughDeck fabricated platforms and weldments are warranted against defects in materials and workmanship for five (5) years.
  • Page 15 230 W. Coleman St. • Rice Lake, WI 54868 • USA U.S. 800-472-6703 • Canada/Mexico 800-321-6703 • International 715-234-9171 • Europe +31 (0)26 472 1319 ww.ricelake.com www.ricelake.mx www.ricelake.eu www.ricelake.co.in m.ricelake.com October 24, 2014 PN 114975 Rev B © Rice Lake Weighing Systems...

Table of Contents