Index to numbered items in Figure 2-5, Figure 2-6, Figure 2-7 and Figure 2-8.
1.
Work tube (diameter customer option)
2.
Extended work tube support bracket
3.
Extended work tube slide bracket
4.
Work tube adaptor plates (adaptor plates for 25mm, 43mm and 63mm OD work tubes are
supplied in a kit, select the correct ones to suit the work tube outside diameter)
5.
Work tube support boss (this is size dependent on work tube diameter)
"O" ring
6.
7.
Clamp ring
8.
Clamp
9.
M6 screw knob
10.
Furnace mounting cradle
11.
Washer M6
12.
Fixing screws M6x16 dome cap screw
13.
Extended work tube guard
14.
Gas/vacuum end seal option (fitting instructions: Installation, Operation & Maintenance
Instructions Tube End Seal Gas and Vacuum Application MF64)
 If gas/vacuum end seals (14) (Figure 2-7, page 7) are required, follow the separate fitting
instructions supplied with the end seals (Installation, Operation & Maintenance
Instructions Tube End Seal Gas and Vacuum Application MF64) .If not, fit the end guard
(13) by sliding it on and holding in place by the screw knobs (9).
Figure 2-7. Cutaway view showing the extended work
tube option with gas/vacuum end seals fitted.
Figure 2-8. EHA furnace with the extended work tube, gas/vacuum
end seal, work tube support and end guard options fitted.
MF65-1.01