Sequence Of Operations; Switching Sequence / Automatic - ABB Zenith ZTX Series Operation, Maintenance, And Installation Manual

Automatic transfer switches
Hide thumbs Also See for Zenith ZTX Series:
Table of Contents

Advertisement

24
Z e n i t h Z T X S e r i e s AT S , O P E R AT I O N , M A I N T E N A N C E , A N D I N S TA L L AT I O N G U I D E

2.5 Sequence of Operations

2.5.1 Switching sequence / Automatic

2.5.1.1 SOURCE 1 Priority
(SOURCE 2 = Generator)
The switching sequence can be
summarized in the following steps:
• An anomaly occurs on SOURCE 1
• Override momentary S1 outage delay
• Generator start
• SOURCE 2 OK
• Transfer from S1 to S2 delay
• Transfer switch (SOURCE 2) to
position II
The re-transfer sequence can be
summarized in the following steps:
• SOURCE 1 is restored
• Transfer from S2 to S1 delay
• Transfer switch (SOURCE 1) to
position I
• Generator stop delay
• Generator stop
• SOURCE 2 off

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents