Commissioning notes
Reference
Environmental conditions
Mechanical check
Electrical check
Functional check
GSD121.1A
GSD126.1A
GSD321.1A
GSD326.1A
Internal Diagrams
Siemens
Smart Infrastructure
For commissioning, the following reference documentation must be available::
• This data sheet.
• HVAC job diagram.
Check to ensure that all permissible values as contained in the section "Technical
data" have been observed.
• Check for proper mounting and ensure that all mechanical settings correspond
to the plant-specific requirements. Additionally, ensure that the dampers are
tightly closed when in the closed position.
• Check the direction of rotation.
• Fasten the actuator securely to avoid twisting and blocking of the actuator.
• Check to ensure that the cables are connected in accordance with the plant
wiring diagram (see "Wiring diagrams").
• The operating voltage AC/DC 24 V (SELV/PELV) or AC 230 V must be within
the tolerance values.
Power supply AC/DC 24 V wires red (1), black (2)
Positioning signal AC/DC 0 V
• Wire orange (7) ON:
• Wire orange (7) OFF:
Power supply AC 230 V wires brown (3), blue (4)
Positioning signal AC 230 V
• Wire white (7) ON:
• Wire white (7) OFF:
G0
Y
G0
GSD12..1A
Air damper actuators GSD...1
Actuator turns counter-clockwise
Actuator turns clockwise
Actuator turns counter-clockwise
Actuator turns clockwise
Y
GSD32..1A
Y
Y
7 / 9
CE2N4603en
2019-11-25