S8E V2.5 Hi-Carb
Superchiller
230V / 50Hz
Installation, Operation &
Service Manual
www.lancerbeverage.com

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the LANCER S8E V2.5 Hi-Carb Superchiller and is the answer not in the manual?

Questions and answers

abdul mafizul
May 28, 2025

Hi. i need some assistance in increasing the efficiency of the super chiller. how can i do this.

1 comments:
Mr. Anderson
May 28, 2025

To increase the efficiency of the Hoshizaki S8E V2.5 Hi-Carb Superchiller:

1. Ensure Proper Insulation: Insulate all lines from the python to the Superchiller connections to prevent condensation.

2. Extend Soda Circuit for High Volume Use: For short python lengths in high-volume accounts, connect the two spare lines in the python to the soda return line to create a double pass of the soda circuit. This provides additional soda reserve.

3. Annual Maintenance:
- Inspect and clean the water bath, coils, and agitator to remove algae or slime.
- Check and clean the recirculation pump strainers; replace if necessary.
- Refill the tank with clean water until it overflows.

4. Check Pump Flow: Ensure the recirculation pump provides at least 5 litres per minute. Replace the pump if the flow is lower.

5. Sanitise Annually: Clean and sanitise the Superchiller and beverage system components yearly to maintain product quality.

6. Correct CO₂ Pressure: Set the CO₂ regulator to 550 kPa for proper carbonator operation.

7. Use Correct Power Supply: Ensure the unit is connected to a 10 amp (Postmix) and a 15 amp (Refrigeration) power supply as specified.

8. Avoid New Carbon Filter Water: Do not use water from a newly installed carbon filter when filling the unit, as it may affect ice bank control.

This answer is automatically generated

Subscribe to Our Youtube Channel

Summary of Contents for Hoshizaki LANCER S8E V2.5 Hi-Carb Superchiller

  • Page 1 S8E V2.5 Hi-Carb Superchiller 230V / 50Hz Installation, Operation & Service Manual www.lancerbeverage.com...
  • Page 2 This page is intentionally left blank www.lancerbeverage.com Page 2 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 3: Table Of Contents

    Trouble Shooting ........................ 21 11.1 Refrigeration ....................... 21 www.lancerbeverage.com Page 3 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 4 Certificate of Warranty ....................... 30 Manufacturer’s Checklist ....................31 www.lancerbeverage.com Page 4 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 5: Introduction

    2. The Company Hoshizaki Lancer is a wholly owned subsidiary of Lancer Corporation, a world leader in the supply of Beverage Dispensing Equipment based in San Antonio, Texas. Lancer has manufacturing bases and distribution networks in 97 countries.
  • Page 6: Specifications

    Casters (79602411) – height with casters approx. 921mm. www.lancerbeverage.com Page 6 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 7: Superchiller Safety Information

    Page 7 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 8: Service & Maintenance

    Page 8 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 9: Installation

    Installation should only be performed by a qualified and competent technician. www.lancerbeverage.com Page 9 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 10: Mounting Superchiller

    PYTH ON 10mm 'U' BEND SODA RETURN www.lancerbeverage.com Page 10 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 11: Connecting To Water Supply

    Page 11 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 12: Plumbing The Drain And Co Exhaust

    Page 12 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary.
  • Page 13: Scheduled Maintenance

    Open carbonator relief valve to purge CO2 and check leakage, close relief valve after checking. www.lancerbeverage.com Page 13 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary.
  • Page 14: Yearly

    BIB's. Operate dispensing valves until syrup flows freely. www.lancerbeverage.com Page 14 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 15: Postmix Circuit Diagram

    8.1. Single Carbonator Superchiller (3 pumps) www.lancerbeverage.com Page 15 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 16: Twin Carbonator Superchiller (4 Pumps)

    SODA RELIEF SODA RELIEF VALVE VALVE www.lancerbeverage.com Page 16 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 17: Twin Carbonator Superchiller (5 Pumps)

    SODA RELIEF SODA RELIEF VALVE VALVE www.lancerbeverage.com Page 17 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 18: Electrical Circuit Diagram

    9. Electrical Circuit Diagram 9.1. Refrigeration Wiring Diagram www.lancerbeverage.com Page 18 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 19: Postmix Wiring Diagram

    S8E V2.5 Hi-Carb Superchiller 230V / 50Hz 9.2. Postmix Wiring Diagram www.lancerbeverage.com Page 19 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 20: Airflow Diagram

    S8E V2.5 Hi-Carb Superchiller 230V / 50Hz 10. Airflow Diagram www.lancerbeverage.com Page 20 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 21: Trouble Shooting

    Fan not operating. Remove obstruction or replace motor. www.lancerbeverage.com Page 21 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 22: Troubleshooting - Postmix

    (install water pressure regulator if necessary) www.lancerbeverage.com Page 22 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 23 Page 23 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 24: Hydra Icebank Control Go/No Go Test

    (Simulates ice growth over black probe only) www.lancerbeverage.com Page 24 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 25: Hydra Carbonator Level Control Test

    (i.e. Water level drops below low level) www.lancerbeverage.com Page 25 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 26: Assembly Diagrams & Parts List

    78000100 PUMP SS MAG WITH CLAMP www.lancerbeverage.com Page 26 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 27: Postmix Assembly Diagram

    S8E V2.5 Hi-Carb Superchiller 230V / 50Hz 14.2. Postmix Assembly Diagram www.lancerbeverage.com Page 27 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 28: Refrigeration Spare Parts List

    PANEL REAR S8E V2 61000487 PANEL RH 5 PUMP www.lancerbeverage.com Page 28 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 29: Refrigeration Assembly Diagram

    S8E V2.5 Hi-Carb Superchiller 230V / 50Hz 14.4. Refrigeration Assembly Diagram www.lancerbeverage.com Page 29 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...
  • Page 30: Certificate Of Warranty

    S8E V2.5 Hi-Carb Superchiller 230V / 50Hz 15. Certificate of Warranty It is the policy of Hoshizaki to provide to its current customers, warranty for all equipment supplied and installation work performed within a specified period. Parts and Equipment Lancer provides a warranty period of twelve (12) months from the date of original invoice for all manufactured parts and the associated labour.
  • Page 31: Www.lancerbeverage.com

    Copy checklist & file, put manual/checklist and pump insulator kit in plastic bag & place in the tank area. Customer asset No. W/O ..............www.lancerbeverage.com Page 31 of 31 Hoshizaki Lancer reserve the right to change specifications without notice. Part No: 68000016 Images are for illustration purposes only as product may vary. No 038 – 21 October 2014...